We have a table which has Datetime stamp field when that record was created. How can we create a trigger or procedure to delete a record after 30 days?
Is there any advice how we can run this deletion scheduler?

Firebird doesn't have a scheduler. You will need to create an application that executes a clean up routine on a schedule yourself. You could do this as part of the normal application, or you could write a small application specifically for this purpose, and execute it with the scheduler of your OS (e.g. Windows Scheduled Tasks, or Linux Cron).

Firebird 2.1 introduced global triggers fired on database connection/disconnection and on transaction starting/ending.
https://www.firebirdsql.org/file/documentation/chunk/en/refdocs/fblangref30/fblangref30-ddl-trigger.html
While it is not exactly what you need it can be used to achieve similar results. Whether that similarity is good enough for you or not is for you to evaluate.
to delete a record after 30 days?
The question here is what you do specifically mean here. Would it still be okay, if the row is deleted in 31 day, in 40 days?
In our case, for a client-server office application, there was no time pressure and additionally there was no safe deletion as long as the programs had "documents" open.
We had to delete some global data, and while there were some marks in the database, which documents use them and which documents are currently opened - it was not very reliable. Which also meant that existing method of immediate delete occasionally could lead to application crashes.
So we reformulated a problem similar to yours the following way:
We need rows not deleted immediately but pending for deletion for 30 days or more. Those record would be rendered in the application in a special way, as a warning to users and also providing a way for them to cancel deletion, if they changed their mind (or if other users had different ideas).
The deletion would happen, in logic terms, "when there is no connected application". In technical term it could mean either "when first application is connecting, but before it started actual (business-related) work" or "when last application is disconnecting, after it ended doing actual work". We settled on the latter, we used on disconnect global database trigger.
We had not only main business-domain application, but a number of technical helper utilities. From the Firebird point of view there is no difference in them. So we had to modify "login sequence" in our main application: right after successful login it registered it's own CURRENT_CONNECTION into a special table. This is potentially slightly fragile.
ON DISCONNECT trigger used to do three actions:
it checked, if current_connection is in the table, and if it was - it called a special stored procedure, SP_LOCAL_CLEANUP.
it removed the current_connection from the table (it could had been BEFORE DELETE trigger then to call the procedure, but we decided our helper utilities should have a way to hook in, if they would need, so the call was put in the ON DISCONNECT trigger).
it checked if that table (known connected business-domain applications list) became empty, and if it did - called another special stored procedure, SP_GLOBAL_CLEANUP.
Those stored procedures were "umbrella" procedures, solely consisted of calls to different procedures, which did the actual work of checking for inconsistencies and fixing them. Like, removing marks "this document is opened for editing" if an application (or computer, or network) has crashed without removing the lock normal way. This way we could add or remove functionality without breaking Firebird object dependency chains.
In particular, one of the global sub-procedures looked into the "deletion pending" records, and deleted those "kept in recycle bin" for a time span running over 30 days. Actually, the records just had a column of planned deletion date and that could be more or less than 30 days, but that is technicality.
This meant that the actual deletion was happening "sometimes after 30 days" and it only happened when all main apps were shut down. When later those apps would be run again - they would re-read those global dictionaries tables in the updated, pruned state. The applications never again were in inconsistent state, using records removed from the database.
Potential fragile point: if users would not shut down application in the night, but just go home, it could mean there would never be a state "last application disconnected". This, however, would be a maintenance nightmare for their network admins (Windows updates and reboots, antivirus updates and reboots), so we documented the recommendation that those admins have to make sure at least once a week all the users went all together out of the database.
Potential fragile point: if the Firebird server crashes (not applications, but the server engine), then the "known connections" table would have stale values. We considered it not a practical problems, as then CURRENT_CONNECTION would be restarted as 1 value and go upward, eventually cleaning the table. But we also added a function into helper app, to use SYSDBA and monitoring tables and clean the table off non-existing connections.
You can re-use this framework if you do not have time pressure and you are okay if the actual deletion is deferred for a few days.
You can also use ON TRANSACTION START trigger instead, to shorten the delay to mere minutes, but I expect this would slow down your application badly, so would suggest against it.

Related

Load balancing SQL reads while batch-processing?

Given an SQL table with timestamped records. Every once in a while an application App0 does something like foreach record in since(certainTimestamp) do process(record); commitOffset(record.timestamp), i.e. periodically it consumes a batch of "fresh" data, processes it sequentially and commits success after each record and then just sleeps for reasonable time (to accumulate yet another batch). That works perfect with single instance.. however how to load balance multiple ones?
In exactly the same environment App0 and App1 concurrently competite for the fresh data. The idea is that ready query executed by the App0 must not overlay with the same read query executed by the App1 - such that they never try to process the same item. In other words, I need SQL-based guarantees that concurrent read queries return different data. Is that even possible?
P.S. Postgres is preferred option.
The problem description is rather vague on what App1 should do while App0 is processing the previously selected records.
In this answer, I make the following assumptions:
all Apps somehow know what the last certainTimestamp is and it is the same for all Apps whenever they start a DB query.
while App0 is processing, say the 10 records it found when it started working, new records come in. That means, the pile of new records with respect to certainTimestamp grows.
when App1 (or any further App) starts, the should process only those new records with respect to certainTimestamp that are not yet being handled by other Apps.
yet, if on App fails/crashes, the unfinished records should be picked the next time another App runs.
This can be achieved by locking records in many SQL databases.
One way to go about this is to use
SELECT ... FOR UPDATE SKIP LOCKED
This statement, in combination with the range-selection since(certainTimestamp) selects and locks all records matching the condition and not being locked currently.
Whenever a new App instance runs this query, it only gets "what's left" to do and can work on that.
This solves the problem of "overlay" or working on the same data.
What's left is then the definition and update of the certainTimestamp.
In order to keep this answer short, I don't go into that here and just leave the pointer to the OP that this needs to be thought through properly to avoid situations where e.g. a single record that cannot be processed for some reason keeps the certainTimestamp at a permanent minimum.

Oracle can return time out when another connection already use the same table?

if i need run an DML (insert, update, delete) in one table of database, firstly he verify if has an active DML using that table. In this momment, if has another operation, my connection wait he has finished.
There's a way to get an "time out" in this cases? Not in a global mode, only for specific cases.
--Edit for more specifications of the problem
Not sure if any kind of lock is actually used. But in my case, there is an old application in Oracle Forms and a new application written by me.
The problem is that when the user opens a specific record to update any field in the old application, and i try to edit the same record in my app, the line is blocked.
So my app it's waiting for the unlock. But the problem is that the user thinks the application is frozen and kill him, losing the changes.
But this is not the case if another Oracle Forms application attempts to edit. When it does, Oracle Forms displays the message "Could not reserve record (2). Keep trying?". Maybe it's because this old app uses any kind of lock. But i need validate this in the code.
Obs: The number 2 is the number of tries to update.
If you do a 'lock table .... wait', then it will wait until any DML on this table that is inflight commits, then gives you the lock. This will make any one coming after you wait till you release the lock. Look at the doc to see how to use this.
Then there's the possibility of locking a single row (select for update). which is more granular.
That being said, can you please explain what are you exactly trying to do? As you may not need to do this at all.

Firebird lock table / lock record

Suppose you have one table for a Desktop application and several users.
When a user opens a record, i want to lock this record. I have tried "WITH LOCK" statement. It works fine.
But when a second users want to update the same record, i want to put a message "Sorry, you cannot work on this order because it is locked. Somebody else has opened this record before you". Firebird waits the first user to commit/rollback. I don t want to wait. I want to put an error message. Is there a simple way to ask firebird record lock status ?
Is there a way to lock a full table ? Or to put a semaphore/mutex (like get_lock on mysql)
i have tried reserving on set transaction statement but it does not work.
My wish is to display a message to the user. Not waiting.
Thanks
If you don't want to wait, then configure your transaction to use NO WAIT, or a wait timeout. However controlling business rules like this through database transactions is not advisable as it requires long running transactions which inhibit garbage collection, increases the chain of interesting transactions, and increases the chance of update conflicts.
I'd advise to use different options like:
First to update wins
Change detection (eg by a timestamp or record version counter which is also used as a condition in the update statement), and allowing the user to overwrite or abandon his update (or maybe merge)
Explicit reservation by updating the record (setting the username) in a separate transaction. This might require cleanup or the ability for a user to break the reservation (eg if someone had it open for too long).
Note that Firebird uses multi version concurrency control (MVCC), so explicit locking is not really natural. See also this answer to Locking tables firebird, delphi.
Locking tables using RESERVING should be possible, but I have never used it, so I am not entirely sure how to use it although you probably also need to specify FOR PROTECTED READ (see Interbase 6.0 Embedded SQL Guide, pages 70/71).

Programmatically purge document deletion

I've a database with an agent that periodically delete (via Java agent, "removePermanently" method) all documents in a view and re-create them.
After some month, i've noticed that database size is considerably increased.
Showing database information through this command
sh database <dbpath>
it results that i've a lot of deleted documents (i suppose they are deletion stubs)
Document Type Live Deleted
Documents 1,922 817,378
Compacting database, 80% space was recovered.
Is there a way to programmatically delete stubs definitively to avoid "database explosion"? Or, is there a way to correctly manage this scenario (deletion and creation of documents)?
Don't delete the documents! Re-use them. That's the best answer. Seriously. Take the existing documents, clear the fields and set Form := "Obsolete". Modify the selection formula for all your views by appending & Form != "Obsolete" Create a new hidden view called "Obsolete" with selection formula Form = "Obsolete", and instead of creating new documents, change your code to go to the Obsolete view, grab an available document and set new field values (including changing the Form field). Only create new documents if there are not enough available in the Obsolete view. Any performance that you lose by doing this, which really should be minimal with the number of documents that you seem to have, will be more than offset by what you will gain by avoiding the growth and fragmentation of the NSF file that you are creating by doing all the deletions and creating new documents.
If, however, there's no possible way for you to do that -- maybe some third party tool that is outside of your control is creating the documents -- then it's important to know if the database you are talking about is replicated. If it is replicated, then you must be very careful because purging deletion stubs before all replicas are brought up to date will cause deleted documents to "come back to life" if a replica that has been off-line since before the delete occurs comes back on-line.
If the database is not replicated at all, or is reliably replicated across all replicas quickly, then you can reduce the purge interval. Go to the Replication Settings dialog, find the checkbox labeled "Remove documents not modified in the last __ days". Do not check the box, but enter a small number into the number of days. The purge interval for deletion stubs will be set to 1/3 of this number. So if you set it to 3 the effect will be that stubs are kept for 1 day and then purged, giving you 24 hours to assure that all replicas are up to date. If you need more, set the interval higher, maintaining the 3x multiple as needed. If a server is down for an extended period of time (longer than your purge interval), then adjust your operations procedures so that you will be sure to disable replication of the database to that server before it comes back on line and the replica can be deleted and recreated. Be aware, though, that user replicas pose the same problem, and it's not really possible to control or be aware of user replicas that might go off-line for longer than the purge interval. In any case, remember: do not check the box. To reduce the purge interval for deletion stubs only, just reduce the number.
Apart from this, the only way to programmatically delete deletion stubs requires use of the Notes C API. It's possible to call the required routines from LotusScript, but in my experience once the total number of stubs plus documents gets too high you will likely run into an error and may have to create and deploy a new non-replica copy of the database to get past it. You can find code along with my explanation in the answer to this previous question.
I have to second Richard's recommendation to reuse documents. I recently had a similar project, and started the way you did with deleting everything and importing half a million records every night. Deletion stubs and the growth of the FT index quickly became problems, eating up huge amounts of disk space and slowing performance significantly. I tried to manage the deletion stubs, but I was clearly going against the grain of Domino's architecture.
I read Richard's suggestion here, and adopted that approach. Here's what I did:
1) create 2 views based on form - one for 'active' records, and another for 'inactive' records
2) start the agent by setting autoupdate = false for both views
3) use stampall("form", "inactive") to change all fo the active records to inactive
4) manually refresh the 2 views using notesview.refresh()
5) start importing data. for each record, pull a document out of the pool of inactive records (by walking the 'inactive' view)
6) if if run out of inactive records in the pool, create new ones
7) when import is complete, manually refresh the views again
8) use db.createftindex(0, true) to re-create the FT index
the code is really not that complex, and it runs in about the same amount of time, if not faster, than my original approach.
Thanks Richard!
Also, look at the advanced db properties - several things there that will help optimize the db.
It sounds like you are "refreshing" the contents of the database by periodically deleting all the documents and creating new ones from some other source. Cut that out. If the data are in the Notes database already, leave the document alone. What you're doing is very inefficient.

What locks are enforced by SQL Server 2005 Express?

Consider a web page having grid-view connected to SqlDataSource having all permission to insert update and delete.
Publish the web page.
This is all on one computer local
Now
opening website on browser A - pressing edit of grid-view
opening website on broswer B - pressing edit of grid-view.
Now I edit in both browsers and press update one by one fine no problem
The last update is the one retained.
But hypothetical situation:
what if there were two computers, or
what if I had two mouse pointers controlled by two independent mice
Computer has capability of running two apps at the same time
Both users get ready and press the update in the browsers at the same time
Even if you consider two different computers this is not possible but for this question
Consider it as possible
Update from two different sources to the same database same table same same row
At the same time, same second, same micro second no delay, both hit the database server at the same time.
What will happen?
In theory I have studied that database management software implement locks when writing no reading, no other writing, etc but does SQL Server 2005 Express implement locks in practical or is it assumed that situation like above will never occur?
If locks there please provide explanation or resource which would explain it keeping in view different scenarios of access
Thank you
edit:-- I am not using control like sqldatasource so please when by providing statements to avoid bling update
its like-- algo---
sqlconnection conn=new .....
sqlcommand
command text is "sql statement for updating values of a particular row"
conn.Open();
cmd.ExecuteNonQuery();
conn.close;
so as seen how can I define the check that before executenonquery that if the data is recently changed are you sure you want to proceed? or something
I am kind of confused here I think..
}
This is solved by most applications using Optimistic Concurency control. Applications simply add more conditions to the update WHERE clause in order to detect changes that occured between the time the data was read and the moment the update is applied. Is called optimistic concurency because the applicaiton assumes no concurent changes will occur, and if they do occur they are are detected and the appplicaiton has to restart the operation. The alternative to optimistic concurency is pesimistic concurency where the applications explicitly locks the data it plans to update. In practice operaitons involving user interaction are never done under pesimistic concurency model.
Other concurency model, specially in distributed applications, is the one implied by the Fiefdom and Emissaries model.
So while database locks and transaction concurency models are always omnipresent in any database operation, when user interaction is involved no application will ever rely on the database locks. User interactions are simply way to long in terms of database transactions. Acquiring locks for the while forgetful Fred is out to lunch and has a data screen open on his desktop simply doesn't work.
SQL 2005 will enforce locks. Before a row can be updated the transaction must acquire an exclusive lock on it. Only 1 transaction can be granted this at a time so the other one will have to wait for that transaction to commit (2 phase locking) before being granted the lock that it needs for the update.
The second write will "win" in that it will overwrite the first one. You can implement optimistic concurrency controls in the sqldatasource to detect that the row has changed and abort the second one rather than blindly overwriting the first edit.
Edit
Following clarification to the question. If you want to roll your own you could add a timestamp column to the table (In SQL Server 2005 this is updated automatically when a row is updated) and bring that back as a hidden dataitem in the gridview then in your UPDATE statement add a where clause UPDATE ... WHERE PrimaryKeyColumn=#PKValue AND TimeStampCol=#OriginalTimestampValue If no rows were affected (retrievable from ExecuteNonQuery - generally) then another transaction modified the row. This might be a bit more lightweight than the alternative used by the data source control where it passes back the original values of all columns and adds them into the WHERE clause with similar logic.