SELECT
CONVERT(VARCHAR, DATEADD(dd, - 1, GETDATE()), 103) AS Date,
'Sales Orders' AS Type,
COUNT(o.SalesOrderID) AS Orders,
SUM(d.QtyOrdered) AS Chairs,
ISNULL(ROUND(SUM(d.ExtendedPrice), 2), 0) AS [Total Ex GST]
FROM
dbo.SalesOrder o
LEFT OUTER JOIN
dbo.SalesOrderDetails d ON o.SalesOrderID = d.SalesOrderID
WHERE
(o.EntryDate >= CONVERT(CHAR(8), DATEADD(dd, - 1, GETDATE()), 112))
AND (o.EntryDate < CONVERT(CHAR(8), GETDATE(), 112))
AND (o.CustomerID <> 187);

You can use datediff(dd,0,getdate()) % 7 = 0 to determine if the current date is a Monday regardless of any other server settings (this is because the zero date in SQL Server is 1900-01-01 which happens to be a Monday).
declare #start date;
declare #finish date;
set #start = dateadd(dd, case when datediff(dd,0,getdate()) % 7 = 0 then -3 else -1 end, getdate());
set #finish = dateadd(dd,1,#start);
select
#start, datename(weekday,#start)
, #finish, datename(weekday,#finish)
, datename(weekday,getdate())
;
So in your query I would use:
declare #start date;
declare #finish date;
set #start = dateadd(dd, case when datediff(dd,0,getdate()) % 7 = 0 then -3 else -1 end, getdate());
set #finish = dateadd(dd,1,#start);
SELECT
CONVERT(VARCHAR, #start, 103) AS Date,
'Sales Orders' AS Type,
COUNT(o.SalesOrderID) AS Orders,
SUM(d.QtyOrdered) AS Chairs,
ISNULL(ROUND(SUM(d.ExtendedPrice), 2), 0) AS [Total Ex GST]
FROM
dbo.SalesOrder o
LEFT OUTER JOIN
dbo.SalesOrderDetails d ON o.SalesOrderID = d.SalesOrderID
WHERE
o.EntryDate >= #start
AND o.EntryDate < #finish
AND o.CustomerID <> 187
;

If you use a case statement to determine how many days in the past you need to go e.g.
dateadd(dd, case when datepart(weekday,getdate()) = 1 then -3 else -1 end, getdate()) -- StartDate
dateadd(dd, case when datepart(weekday,getdate()) = 1 then -2 else 0 end, getdate()) -- EndDate
so your code would look like
SELECT
CONVERT(VARCHAR, dateadd(dd, case when datepart(weekday,getdate()) = 1 then -3 else -1 end, getdate()), 103) AS Date,
'Sales Orders' AS Type,
COUNT(o.SalesOrderID) AS Orders,
SUM(d.QtyOrdered) AS Chairs,
ISNULL(ROUND(SUM(d.ExtendedPrice), 2), 0) AS [Total Ex GST]
FROM
dbo.SalesOrder o
LEFT OUTER JOIN
dbo.SalesOrderDetails d ON o.SalesOrderID = d.SalesOrderID
WHERE
(o.EntryDate >= CONVERT(CHAR(8), dateadd(dd, case when datepart(weekday,getdate()) = 1 then -3 else -1 end, getdate()), 112))
AND (o.EntryDate < CONVERT(CHAR(8), dateadd(dd, case when datepart(weekday,getdate()) = 1 then -2 else 0 end, getdate()), 112))
AND (o.CustomerID <> 187);
PS: Do confirm that weekday 1 is Monday on your server.

Related

Get the remaining days between two dates

I am trying to calculate the remaining year, month and days between 2 dates using the method below, but I cannot get the remaining dates right. Is there a function or different method I should try?
Select (DATEDIFF(m, '1965-10-17', '2021-04-07')) /12 as AgeYr ,
(DATEDIFF(m, '1965-10-17', '2021-04-07')) %12 as AgeMth,
(DATEDIFF(d, '1965-10-17', '2021-04-07')) %30 as AgeDay;
This is the result of my code
AgeYr
AgeMth
AgeDay
55
6
10
but the result should be
AgeYr
AgeMth
AgeDay
55
6
21
DECLARE #date datetime, #startdate datetime, #enddate datetime, #years int, #months int, #days int
SELECT #startdate = '1965-10-17'
SELECT #enddate = '2021-04-07'
SELECT #date = #startdate
SELECT #years = DATEDIFF(yy, #startdate, #enddate) - CASE WHEN (MONTH(#date) > MONTH(#enddate)) OR (MONTH(#date) = MONTH(#enddate) AND DAY(#date) > DAY(#enddate)) THEN 1 ELSE 0 END
SELECT #startdate = DATEADD(yy, #years, #startdate)
SELECT #months = DATEDIFF(m, #startdate, #enddate) - CASE WHEN DAY(#date) > DAY(#enddate) THEN 1 ELSE 0 END
SELECT #startdate = DATEADD(m, #months, #startdate)
SELECT #days = DATEDIFF(d, #startdate, #enddate)
SELECT #years years, #months months, #days days
Output:
AgeYr
AgeMth
AgeDay
55
5
21
db<>fiddle here
You can also do it with common table expression:
;with years as
(SELECT (DATEDIFF(yy, '1965-10-17', '2021-04-07') - CASE WHEN (MONTH('1965-10-17') > MONTH('2021-04-07')) OR (MONTH('1965-10-17') = MONTH('2021-04-07') AND DAY('1965-10-17') > DAY('2021-04-07')) THEN 1 ELSE 0 END)AgeYr,
'1965-10-17' startdate)
,months as
(SELECT (DATEDIFF(m, DATEADD(yy, years.AgeYr, '1965-10-17'), '2021-04-07') - CASE WHEN DAY('1965-10-17') > DAY('2021-04-07') THEN 1 ELSE 0 END)AgeMth, DATEADD(yy, years.AgeYr, '1965-10-17') temp
from years)
,days as
(select DATEDIFF(d, DATEADD(m, months.AgeMth, temp), '2021-04-07')AgeDay from months)
select years.AgeYr,months.AgeMth,days.AgeDay from years,months,days
Output:
AgeYr
AgeMth
AgeDay
55
5
21
db<>fiddle here

TSQL only pull data if another date field is the previous business day

1) I'm need only to pull data if the the openddate is equal to the PrevBiz date. I think the where/and statement would be Openddate = PrevBiz, but not sure. It wasn't working for me and could be because the date format isn't matching. Any Suggestions?
DECLARE #TODAY DATE = GETDATE()
DECLARE #PREVFIRST CHAR(8) = CONVERT(CHAR(8), DATEADD(MONTH, DATEDIFF(MONTH, 0, GETDATE()) - 1, 0), 112)
DECLARE #PREVLAST CHAR(8) = CONVERT(CHAR(8), DATEADD(MONTH, DATEDIFF(MONTH, 0, GETDATE()), -1), 112)
DECLARE #PREVBIZ CHAR(12) = DATEADD(DAY, CASE DATENAME(WEEKDAY, CONVERT(CHAR(12), #TODAY,112))
WHEN 'SUNDAY' THEN -2
WHEN 'MONDAY' THEN -3
ELSE -1 END, DATEDIFF(DAY, 0, CONVERT(CHAR(12), #TODAY, 112)))
SELECT TOP 10
CURRENTDATE =#TODAY,
FIRST_OF_MONTH =#PREVFIRST,
LASTDAY_OFMONTH =#PREVLAST,
PREVBIZ =#PREVBIZ,
DATEADD(DAY, CASE DATENAME(WEEKDAY, CONVERT(DATE, #TODAY,101))
WHEN 'SUNDAY' THEN -2
WHEN 'MONDAY' THEN -3
ELSE -1 END, DATEDIFF(DAY, 0, CONVERT(DATE, #TODAY, 101))) AS PREVIOUSBIZDATE,
OpendDate
FROM [USBI_DW].[USBI].[vw_NameAddressBase]
where IsCurrent = 1
Here's my results:
declare #TODAY datetime = convert(date,GETDATE())
declare #PREVBIZ datetime = DATEADD(DAY, CASE DATENAME(WEEKDAY,#TODAY)
WHEN 'SUNDAY' THEN -2
WHEN 'MONDAY' THEN -3
ELSE -1 END,#TODAY)
declare #iToday int = convert(nvarchar(8),#TODAY, 112)
, #iPrevBiz int = convert(nvarchar(8),#PREVBIZ, 112)
select top 10
CURRENTDATE =#iToday,
PREVBIZ =#iPrevBiz,
OpendDate
from [USBI_DW].[USBI].[vw_NameAddressBase]
where IsCurrent = 1
and OprendDate = #iPrevBiz
hope your view contains int date attribute ( because of DateWarehouse specific)

DATEDIFF between two dates, excluding two specific days

In Dubai, the standard weekend runs from Friday - Saturday rather than the traditional Saturday / Sunday.
I am trying to calculate the amount of working days between two given dates, and this is the code I have;
DATEDIFF(dd, DATEADD(hour, DATEDIFF(hh, getdate(), getutcdate()), #StartDate),
DATEADD(hour, DATEDIFF(hh, getdate(), getutcdate()), #EndDate)+1)
-
(
(DATEDIFF(wk, #StartDate, #EndDate) * 2
+(CASE WHEN DATENAME(dw, #StartDate) = 'Saturday' then 1 else 0 end)
+(CASE WHEN DATENAME(dw, #EndDate) = 'Friday' then 1 else 0 end)
))
)
However it is calculating the wrong amount of days. For example;
When the start date is 02-03-2016 and the end date is 02-06-2016 the returns as 4, but it should be 2.
When the start date is 02-03-2016 and the end date is 02-07-2016 the result is 3 which is correct.
The code below calculates the working days from your examples correctly. You can wrap it in a scalar function if you want.
declare #from date, #to date;
set #from = '2016-02-03';
set #to = '2016-02-06';
with dates(date)
as
(
select #from
union all
select dateadd(dd, 1, [date])
from dates
where [date] < #to
)
select count(*) [working days]
from (
select date, case when datename(dw, [date]) in ('Friday', 'Saturday') then 0 else 1 end as working
from dates) as dt
where dt.working = 1

SQL DateDiff advanced usage?

I need to calculate the DateDiff (hours) between two dates, but only during business-hours (8:30 - 16:00, no weekends). This result will then be put into the Reaction_Time column as per the example below.
ID Date Reaction_Time Overdue
1 29.04.2003 15:00:00
1 30.04.2003 11:00:00 3:30
2 30.04.2003 14:00:00
2 01.05.2003 14:00:00 7:30 YES
*Note: I didn't check to see if the dates in example were holidays.
I'm using SQL Server 2005
This will be combined with a bigger query, but for now all I need is this to get started, I'll try to figure out how to put it all together on my own. Thanks for the help!
Edit: Hey, thanks everyone for the replies. But due to the obvious complexity of a solution on SQL side, it was decided we would do this in Excel instead as that's where the report will be moved anyway. Sorry for the trouble, but I really figured it would be simpler than this. As it is, we just don't have the time.
I would recommend building a user defined function that calculates the date difference in business hours according to your rules.
SELECT
Id,
MIN(Date) DateStarted,
MAX(Date) DateCompleted,
dbo.udfDateDiffBusinessHours(MIN(Date), MAX(Date)) ReactionTime
FROM
Incident
GROUP BY
Id
I'm not sure where your Overdue value comes from, so I left it off in my example.
In a function you can write way more expressive SQL than in a query, and you don't clog your query with business rules, making it hard to maintain.
Also a function can easily be reused. Extending it to include support for holidays (I'm thinking of a Holidays table here) would not be too hard. Further refinements are possible without the need to change hard to read nested SELECT/CASE WHEN constructs, which would be the alternative.
If I have time today, I'll look into writing an example function.
EDIT: Here is something with bells and whistles, calculating around weekends transparently:
ALTER FUNCTION dbo.udfDateDiffBusinessHours (
#date1 DATETIME,
#date2 DATETIME
) RETURNS DATETIME AS
BEGIN
DECLARE #sat INT
DECLARE #sun INT
DECLARE #workday_s INT
DECLARE #workday_e INT
DECLARE #basedate1 DATETIME
DECLARE #basedate2 DATETIME
DECLARE #calcdate1 DATETIME
DECLARE #calcdate2 DATETIME
DECLARE #cworkdays INT
DECLARE #cweekends INT
DECLARE #returnval INT
SET #workday_s = 510 -- work day start: 8.5 hours
SET #workday_e = 960 -- work day end: 16.0 hours
-- calculate Saturday and Sunday dependent on SET DATEFIRST option
SET #sat = CASE ##DATEFIRST WHEN 7 THEN 7 ELSE 7 - ##DATEFIRST END
SET #sun = CASE ##DATEFIRST WHEN 7 THEN 1 ELSE #sat + 1 END
SET #calcdate1 = #date1
SET #calcdate2 = #date2
-- #date1: assume next day if start was after end of workday
SET #basedate1 = DATEADD(dd, 0, DATEDIFF(dd, 0, #calcdate1))
SET #calcdate1 = CASE WHEN DATEDIFF(mi, #basedate1, #calcdate1) > #workday_e
THEN #basedate1 + 1
ELSE #calcdate1
END
-- #date1: if Saturday or Sunday, make it next Monday
SET #basedate1 = DATEADD(dd, 0, DATEDIFF(dd, 0, #calcdate1))
SET #calcdate1 = CASE DATEPART(dw, #basedate1)
WHEN #sat THEN #basedate1 + 2
WHEN #sun THEN #basedate1 + 1
ELSE #calcdate1
END
-- #date1: assume #workday_s as the minimum start time
SET #basedate1 = DATEADD(dd, 0, DATEDIFF(dd, 0, #calcdate1))
SET #calcdate1 = CASE WHEN DATEDIFF(mi, #basedate1, #calcdate1) < #workday_s
THEN DATEADD(mi, #workday_s, #basedate1)
ELSE #calcdate1
END
-- #date2: assume previous day if end was before start of workday
SET #basedate2 = DATEADD(dd, 0, DATEDIFF(dd, 0, #calcdate2))
SET #calcdate2 = CASE WHEN DATEDIFF(mi, #basedate2, #calcdate2) < #workday_s
THEN #basedate2 - 1
ELSE #calcdate2
END
-- #date2: if Saturday or Sunday, make it previous Friday
SET #basedate2 = DATEADD(dd, 0, DATEDIFF(dd, 0, #calcdate2))
SET #calcdate2 = CASE DATEPART(dw, #calcdate2)
WHEN #sat THEN #basedate2 - 0.00001
WHEN #sun THEN #basedate2 - 1.00001
ELSE #date2
END
-- #date2: assume #workday_e as the maximum end time
SET #basedate2 = DATEADD(dd, 0, DATEDIFF(dd, 0, #calcdate2))
SET #calcdate2 = CASE WHEN DATEDIFF(mi, #basedate2, #calcdate2) > #workday_e
THEN DATEADD(mi, #workday_e, #basedate2)
ELSE #calcdate2
END
-- count full work days (subtract Saturdays and Sundays)
SET #cworkdays = DATEDIFF(dd, #basedate1, #basedate2)
SET #cweekends = #cworkdays / 7
SET #cworkdays = #cworkdays - #cweekends * 2
-- calculate effective duration in minutes
SET #returnval = #cworkdays * (#workday_e - #workday_s)
+ #workday_e - DATEDIFF(mi, #basedate1, #calcdate1)
+ DATEDIFF(mi, #basedate2, #calcdate2) - #workday_e
-- return duration as an offset in minutes from date 0
RETURN DATEADD(mi, #returnval, 0)
END
The function returns a DATETIME value meant as an offset from date 0 (which is "1900-01-01 00:00:00"). So for example a timespan of 8:00 hours would be "1900-01-01 08:00:00" and 25 hours would be "1900-01-02 01:00:00". The function result is the time difference in business hours between two dates. No special handling/support for overtime.
SELECT dbo.udfDateDiffBusinessHours('2003-04-29 15:00:00', '2003-04-30 11:00:00')
--> 1900-01-01 03:30:00.000
SELECT dbo.udfDateDiffBusinessHours('2003-04-30 14:00:00', '2003-05-01 14:00:00')
--> 1900-01-01 07:30:00.000
The function assumes the start of the next available work day (08:30 h) when the #date1 is off-hours, and the end of the previous available work day (16:00 h) when #date2 is off-hours.
"next/previous available" means:
if #date1 is '2009-02-06 07:00:00' (Fri), it will become '2009-02-06 08:30:00' (Fri)
if #date1 is '2009-02-06 19:00:00' (Fri), it will become '2009-02-09 08:30:00' (Mon)
if #date2 is '2009-02-09 07:00:00' (Mon), it will become '2009-02-06 16:00:00' (Fri)
if #date2 is '2009-02-09 19:00:00' (Mon), it will become '2009-02-09 16:00:00' (Mon)
DECLARE #BusHourStart DATETIME, #BusHourEnd DATETIME
SELECT #BusHourStart = '08:30:00', #BusHourEnd = '16:00:00'
DECLARE #BusMinutesStart INT, #BusMinutesEnd INT
SELECT #BusMinutesStart = DATEPART(minute,#BusHourStart)+DATEPART(hour,#BusHourStart)*60,
#BusMinutesEnd = DATEPART(minute,#BusHourEnd)+DATEPART(hour,#BusHourEnd)*60
DECLARE #Dates2 TABLE (ID INT, DateStart DATETIME, DateEnd DATETIME)
INSERT INTO #Dates2
SELECT 1, '15:00:00 04/29/2003', '11:00:00 04/30/2003' UNION
SELECT 2, '14:00:00 04/30/2003', '14:00:00 05/01/2003' UNION
SELECT 3, '14:00:00 05/02/2003', '14:00:00 05/06/2003' UNION
SELECT 4, '14:00:00 05/02/2003', '14:00:00 05/04/2003' UNION
SELECT 5, '07:00:00 05/02/2003', '14:00:00 05/02/2003' UNION
SELECT 6, '14:00:00 05/02/2003', '23:00:00 05/02/2003' UNION
SELECT 7, '07:00:00 05/02/2003', '08:00:00 05/02/2003' UNION
SELECT 8, '22:00:00 05/02/2003', '23:00:00 05/03/2003' UNION
SELECT 9, '08:00:00 05/03/2003', '23:00:00 05/04/2003' UNION
SELECT 10, '07:00:00 05/02/2003', '23:00:00 05/02/2003'
-- SET DATEFIRST to U.S. English default value of 7.
SET DATEFIRST 7
SELECT ID, DateStart, DateEnd, CONVERT(VARCHAR, Minutes/60) +':'+ CONVERT(VARCHAR, Minutes % 60) AS ReactionTime
FROM (
SELECT ID, DateStart, DateEnd, Overtime,
CASE
WHEN DayDiff = 0 THEN
CASE
WHEN (MinutesEnd - MinutesStart - Overtime) > 0 THEN (MinutesEnd - MinutesStart - Overtime)
ELSE 0
END
WHEN DayDiff > 0 THEN
CASE
WHEN (StartPart + EndPart - Overtime) > 0 THEN (StartPart + EndPart - Overtime)
ELSE 0
END + DayPart
ELSE 0
END AS Minutes
FROM(
SELECT ID, DateStart, DateEnd, DayDiff, MinutesStart, MinutesEnd,
CASE WHEN(#BusMinutesStart - MinutesStart) > 0 THEN (#BusMinutesStart - MinutesStart) ELSE 0 END +
CASE WHEN(MinutesEnd - #BusMinutesEnd) > 0 THEN (MinutesEnd - #BusMinutesEnd) ELSE 0 END AS Overtime,
CASE WHEN(#BusMinutesEnd - MinutesStart) > 0 THEN (#BusMinutesEnd - MinutesStart) ELSE 0 END AS StartPart,
CASE WHEN(MinutesEnd - #BusMinutesStart) > 0 THEN (MinutesEnd - #BusMinutesStart) ELSE 0 END AS EndPart,
CASE WHEN DayDiff > 1 THEN (#BusMinutesEnd - #BusMinutesStart)*(DayDiff - 1) ELSE 0 END AS DayPart
FROM (
SELECT DATEDIFF(d,DateStart, DateEnd) AS DayDiff, ID, DateStart, DateEnd,
DATEPART(minute,DateStart)+DATEPART(hour,DateStart)*60 AS MinutesStart,
DATEPART(minute,DateEnd)+DATEPART(hour,DateEnd)*60 AS MinutesEnd
FROM (
SELECT ID,
CASE
WHEN DATEPART(dw, DateStart) = 7
THEN DATEADD(SECOND, 1, DATEADD(DAY, DATEDIFF(DAY, 0, DateStart), 2))
WHEN DATEPART(dw, DateStart) = 1
THEN DATEADD(SECOND, 1, DATEADD(DAY, DATEDIFF(DAY, 0, DateStart), 1))
ELSE DateStart END AS DateStart,
CASE
WHEN DATEPART(dw, DateEnd) = 7
THEN DATEADD(SECOND, -1, DATEADD(DAY, DATEDIFF(DAY, 0, DateEnd), 0))
WHEN DATEPART(dw, DateEnd) = 1
THEN DATEADD(SECOND, -1, DATEADD(DAY, DATEDIFF(DAY, 0, DateEnd), -1))
ELSE DateEnd END AS DateEnd FROM #Dates2
)Weekends
)InMinutes
)Overtime
)Calculation
select datediff(hh,#date1,#date2) - 16.5*(datediff(dd,#date1,#date2))
The only catch is that it will give you 3:30 as 3.5 hours but you can fix that easily.
Use this code : to find out weekend in between dates
(
DATEDIFF(dd, open_date, zassignment_date) + 1
- ( (DATEDIFF(dd, open_date, zassignment_date) + 1)
-(DATEDIFF(wk, open_date, zassignment_date) * 2)
-(CASE WHEN DATENAME(dw, open_date) = 'Sunday' THEN 1 ELSE 0 END)
-(CASE WHEN DATENAME(dw, zassignment_date) = 'Saturday' THEN 1 ELSE 0 END) )) wk_end
Assuming you have a reference-table of the working days (and their hours), then I would use a 3 stage approach (pseudo-sql)
(first preclude the "all in one day" trivial example, since that simplifies the logic)
-- days that are neither the start nor end (full days)
SELECT #FullDayHours = SUM(day start to day end)
FROM reference-calendar
WHERE Start >= midnight-after-start and End <= midnight-before-end
-- time after the [query start] to the end of the first working day
SELECT #FirstDayHours = [query start] to day end
FROM reference-calandar
WHERE start day
-- time from the start of the last working day to the [query end]
SELECT #LastDayHours = day start to [query end]
FROM reference-calendar
WHERE end-day
IF #FirstDayHours < 0 SET #FirstDayHours = 0 -- starts outside working time
IF #LastDayHours < 0 SET #LastDayHours = 0 -- ends outside working time
PRINT #FirstDayHours + #FullDayHours + #LastDayHours
Obviously it is a bit hard to do properly without more context...
This function will give you the difference in business hours between two given times. This will return the difference in minutes or hours based on the date part parameter.
CREATE FUNCTION [dbo].[fnBusinessHoursDateDiff] (#StartTime SmallDatetime, #EndTime SmallDateTime, #DatePart varchar(2)) RETURNS DECIMAL (10,2)
AS
BEGIN
DECLARE #Minutes bigint
, #FinalNumber Decimal(10,2)
-- // Create Minute By minute table for CTE
-- ===========================================================
;WITH cteInputHours (StartTime, EndTime, NextTime) AS (
SELECT #StartTime
, #EndTime
, dateadd(mi, 1, #StartTime)
),
cteBusinessMinutes (TimeOfDay, [isBusHour], NextTime) AS(
SELECT StartTime [TimeOfDay]
, case when datepart(dw, StartTime) between 2 and 6 and convert(time,StartTime) between '08:30' and '15:59' then 1 else 0 end [isBusHour]
, dateadd(mi, 1, #StartTime) [NextTime]
FROM cteInputHours
UNION ALL
SELECT dateadd(mi, 1, (a.TimeOfDay)) [TimeOfDay]
, case when datepart(dw, a.TimeOfDay) between 2 and 6 and convert(time,dateadd(mi, 1, (a.TimeOfDay)) ) between '08:30' and '15:59' then 1 else 0 end [isBusHour]
, dateadd(mi, 2, (a.TimeOfDay)) NextTime
FROM cteBusinessMinutes a
WHERE dateadd(mi, 1, (a.TimeOfDay)) < #EndTime
)
SELECT #Minutes = count(*)
FROM cteBusinessMinutes
WHERE isBusHour = 1
OPTION (MAXRECURSION 0);
-- // Final Select
-- ===========================================================
SELECT #FinalNumber = #Minutes / (case when #DatePart = 'hh' then 60.00 else 1 end)
RETURN #FinalNumber
END

Count work days between two dates

How can I calculate the number of work days between two dates in SQL Server?
Monday to Friday and it must be T-SQL.
For workdays, Monday to Friday, you can do it with a single SELECT, like this:
DECLARE #StartDate DATETIME
DECLARE #EndDate DATETIME
SET #StartDate = '2008/10/01'
SET #EndDate = '2008/10/31'
SELECT
(DATEDIFF(dd, #StartDate, #EndDate) + 1)
-(DATEDIFF(wk, #StartDate, #EndDate) * 2)
-(CASE WHEN DATENAME(dw, #StartDate) = 'Sunday' THEN 1 ELSE 0 END)
-(CASE WHEN DATENAME(dw, #EndDate) = 'Saturday' THEN 1 ELSE 0 END)
If you want to include holidays, you have to work it out a bit...
In Calculating Work Days you can find a good article about this subject, but as you can see it is not that advanced.
--Changing current database to the Master database allows function to be shared by everyone.
USE MASTER
GO
--If the function already exists, drop it.
IF EXISTS
(
SELECT *
FROM dbo.SYSOBJECTS
WHERE ID = OBJECT_ID(N'[dbo].[fn_WorkDays]')
AND XType IN (N'FN', N'IF', N'TF')
)
DROP FUNCTION [dbo].[fn_WorkDays]
GO
CREATE FUNCTION dbo.fn_WorkDays
--Presets
--Define the input parameters (OK if reversed by mistake).
(
#StartDate DATETIME,
#EndDate DATETIME = NULL --#EndDate replaced by #StartDate when DEFAULTed
)
--Define the output data type.
RETURNS INT
AS
--Calculate the RETURN of the function.
BEGIN
--Declare local variables
--Temporarily holds #EndDate during date reversal.
DECLARE #Swap DATETIME
--If the Start Date is null, return a NULL and exit.
IF #StartDate IS NULL
RETURN NULL
--If the End Date is null, populate with Start Date value so will have two dates (required by DATEDIFF below).
IF #EndDate IS NULL
SELECT #EndDate = #StartDate
--Strip the time element from both dates (just to be safe) by converting to whole days and back to a date.
--Usually faster than CONVERT.
--0 is a date (01/01/1900 00:00:00.000)
SELECT #StartDate = DATEADD(dd,DATEDIFF(dd,0,#StartDate), 0),
#EndDate = DATEADD(dd,DATEDIFF(dd,0,#EndDate) , 0)
--If the inputs are in the wrong order, reverse them.
IF #StartDate > #EndDate
SELECT #Swap = #EndDate,
#EndDate = #StartDate,
#StartDate = #Swap
--Calculate and return the number of workdays using the input parameters.
--This is the meat of the function.
--This is really just one formula with a couple of parts that are listed on separate lines for documentation purposes.
RETURN (
SELECT
--Start with total number of days including weekends
(DATEDIFF(dd,#StartDate, #EndDate)+1)
--Subtact 2 days for each full weekend
-(DATEDIFF(wk,#StartDate, #EndDate)*2)
--If StartDate is a Sunday, Subtract 1
-(CASE WHEN DATENAME(dw, #StartDate) = 'Sunday'
THEN 1
ELSE 0
END)
--If EndDate is a Saturday, Subtract 1
-(CASE WHEN DATENAME(dw, #EndDate) = 'Saturday'
THEN 1
ELSE 0
END)
)
END
GO
If you need to use a custom calendar, you might need to add some checks and some parameters. Hopefully it will provide a good starting point.
All Credit to Bogdan Maxim & Peter Mortensen. This is their post, I just added holidays to the function (This assumes you have a table "tblHolidays" with a datetime field "HolDate".
--Changing current database to the Master database allows function to be shared by everyone.
USE MASTER
GO
--If the function already exists, drop it.
IF EXISTS
(
SELECT *
FROM dbo.SYSOBJECTS
WHERE ID = OBJECT_ID(N'[dbo].[fn_WorkDays]')
AND XType IN (N'FN', N'IF', N'TF')
)
DROP FUNCTION [dbo].[fn_WorkDays]
GO
CREATE FUNCTION dbo.fn_WorkDays
--Presets
--Define the input parameters (OK if reversed by mistake).
(
#StartDate DATETIME,
#EndDate DATETIME = NULL --#EndDate replaced by #StartDate when DEFAULTed
)
--Define the output data type.
RETURNS INT
AS
--Calculate the RETURN of the function.
BEGIN
--Declare local variables
--Temporarily holds #EndDate during date reversal.
DECLARE #Swap DATETIME
--If the Start Date is null, return a NULL and exit.
IF #StartDate IS NULL
RETURN NULL
--If the End Date is null, populate with Start Date value so will have two dates (required by DATEDIFF below).
IF #EndDate IS NULL
SELECT #EndDate = #StartDate
--Strip the time element from both dates (just to be safe) by converting to whole days and back to a date.
--Usually faster than CONVERT.
--0 is a date (01/01/1900 00:00:00.000)
SELECT #StartDate = DATEADD(dd,DATEDIFF(dd,0,#StartDate), 0),
#EndDate = DATEADD(dd,DATEDIFF(dd,0,#EndDate) , 0)
--If the inputs are in the wrong order, reverse them.
IF #StartDate > #EndDate
SELECT #Swap = #EndDate,
#EndDate = #StartDate,
#StartDate = #Swap
--Calculate and return the number of workdays using the input parameters.
--This is the meat of the function.
--This is really just one formula with a couple of parts that are listed on separate lines for documentation purposes.
RETURN (
SELECT
--Start with total number of days including weekends
(DATEDIFF(dd,#StartDate, #EndDate)+1)
--Subtact 2 days for each full weekend
-(DATEDIFF(wk,#StartDate, #EndDate)*2)
--If StartDate is a Sunday, Subtract 1
-(CASE WHEN DATENAME(dw, #StartDate) = 'Sunday'
THEN 1
ELSE 0
END)
--If EndDate is a Saturday, Subtract 1
-(CASE WHEN DATENAME(dw, #EndDate) = 'Saturday'
THEN 1
ELSE 0
END)
--Subtract all holidays
-(Select Count(*) from [DB04\DB04].[Gateway].[dbo].[tblHolidays]
where [HolDate] between #StartDate and #EndDate )
)
END
GO
-- Test Script
/*
declare #EndDate datetime= dateadd(m,2,getdate())
print #EndDate
select [Master].[dbo].[fn_WorkDays] (getdate(), #EndDate)
*/
My version of the accepted answer as a function using DATEPART, so I don't have to do a string comparison on the line with
DATENAME(dw, #StartDate) = 'Sunday'
Anyway, here's my business datediff function
SET ANSI_NULLS ON
GO
SET QUOTED_IDENTIFIER ON
GO
CREATE FUNCTION BDATEDIFF
(
#startdate as DATETIME,
#enddate as DATETIME
)
RETURNS INT
AS
BEGIN
DECLARE #res int
SET #res = (DATEDIFF(dd, #startdate, #enddate) + 1)
-(DATEDIFF(wk, #startdate, #enddate) * 2)
-(CASE WHEN DATEPART(dw, #startdate) = 1 THEN 1 ELSE 0 END)
-(CASE WHEN DATEPART(dw, #enddate) = 7 THEN 1 ELSE 0 END)
RETURN #res
END
GO
Another approach to calculating working days is to use a WHILE loop which basically iterates through a date range and increment it by 1 whenever days are found to be within Monday – Friday. The complete script for calculating working days using the WHILE loop is shown below:
CREATE FUNCTION [dbo].[fn_GetTotalWorkingDaysUsingLoop]
(#DateFrom DATE,
#DateTo   DATE
)
RETURNS INT
AS
     BEGIN
         DECLARE #TotWorkingDays INT= 0;
         WHILE #DateFrom <= #DateTo
             BEGIN
                 IF DATENAME(WEEKDAY, #DateFrom) IN('Monday', 'Tuesday', 'Wednesday', 'Thursday', 'Friday')
                     BEGIN
                         SET #TotWorkingDays = #TotWorkingDays + 1;
                 END;
                 SET #DateFrom = DATEADD(DAY, 1, #DateFrom);
             END;
         RETURN #TotWorkingDays;
     END;
GO
Although the WHILE loop option is cleaner and uses less lines of code, it has the potential of being a performance bottleneck in your environment particularly when your date range spans across several years.
You can see more methods on how to calculate work days and hours in this article:
https://www.sqlshack.com/how-to-calculate-work-days-and-hours-in-sql-server/
DECLARE #TotalDays INT,#WorkDays INT
DECLARE #ReducedDayswithEndDate INT
DECLARE #WeekPart INT
DECLARE #DatePart INT
SET #TotalDays= DATEDIFF(day, #StartDate, #EndDate) +1
SELECT #ReducedDayswithEndDate = CASE DATENAME(weekday, #EndDate)
WHEN 'Saturday' THEN 1
WHEN 'Sunday' THEN 2
ELSE 0 END
SET #TotalDays=#TotalDays-#ReducedDayswithEndDate
SET #WeekPart=#TotalDays/7;
SET #DatePart=#TotalDays%7;
SET #WorkDays=(#WeekPart*5)+#DatePart
RETURN #WorkDays
(I'm a few points shy of commenting privileges)
If you decide to forgo the +1 day in CMS's elegant solution, note that if your start date and end date are in the same weekend, you get a negative answer. Ie., 2008/10/26 to 2008/10/26 returns -1.
my rather simplistic solution:
select #Result = (..CMS's answer..)
if (#Result < 0)
select #Result = 0
RETURN #Result
.. which also sets all erroneous posts with start date after end date to zero. Something you may or may not be looking for.
For difference between dates including holidays I went this way:
1) Table with Holidays:
CREATE TABLE [dbo].[Holiday](
[Id] [int] IDENTITY(1,1) NOT NULL,
[Name] [nvarchar](50) NULL,
[Date] [datetime] NOT NULL)
2) I had my plannings Table like this and wanted to fill column Work_Days which was empty:
CREATE TABLE [dbo].[Plan_Phase](
[Id] [int] IDENTITY(1,1) NOT NULL,
[Id_Plan] [int] NOT NULL,
[Id_Phase] [int] NOT NULL,
[Start_Date] [datetime] NULL,
[End_Date] [datetime] NULL,
[Work_Days] [int] NULL)
3) So in order to get "Work_Days" to later fill in my column just had to:
SELECT Start_Date, End_Date,
(DATEDIFF(dd, Start_Date, End_Date) + 1)
-(DATEDIFF(wk, Start_Date, End_Date) * 2)
-(SELECT COUNT(*) From Holiday Where Date >= Start_Date AND Date <= End_Date)
-(CASE WHEN DATENAME(dw, Start_Date) = 'Sunday' THEN 1 ELSE 0 END)
-(CASE WHEN DATENAME(dw, End_Date) = 'Saturday' THEN 1 ELSE 0 END)
-(CASE WHEN (SELECT COUNT(*) From Holiday Where Start_Date = Date) > 0 THEN 1 ELSE 0 END)
-(CASE WHEN (SELECT COUNT(*) From Holiday Where End_Date = Date) > 0 THEN 1 ELSE 0 END) AS Work_Days
from Plan_Phase
Hope that I could help.
Cheers
Here is a version that works well (I think). Holiday table contains Holiday_date columns that contains holidays your company observe.
DECLARE #RAWDAYS INT
SELECT #RAWDAYS = DATEDIFF(day, #StartDate, #EndDate )--+1
-( 2 * DATEDIFF( week, #StartDate, #EndDate ) )
+ CASE WHEN DATENAME(dw, #StartDate) = 'Saturday' THEN 1 ELSE 0 END
- CASE WHEN DATENAME(dw, #EndDate) = 'Saturday' THEN 1 ELSE 0 END
SELECT #RAWDAYS - COUNT(*)
FROM HOLIDAY NumberOfBusinessDays
WHERE [Holiday_Date] BETWEEN #StartDate+1 AND #EndDate
I know this is an old question but I needed a formula for workdays excluding the start date since I have several items and need the days to accumulate correctly.
None of the non-iterative answers worked for me.
I used a defintion like
Number of times midnight to monday, tuesday, wednesday, thursday and friday is passed
(others might count midnight to saturday instead of monday)
I ended up with this formula
SELECT DATEDIFF(day, #StartDate, #EndDate) /* all midnights passed */
- DATEDIFF(week, #StartDate, #EndDate) /* remove sunday midnights */
- DATEDIFF(week, DATEADD(day, 1, #StartDate), DATEADD(day, 1, #EndDate)) /* remove saturday midnights */
This is basically CMS's answer without the reliance on a particular language setting. And since we're shooting for generic, that means it should work for all ##datefirst settings as well.
datediff(day, <start>, <end>) + 1 - datediff(week, <start>, <end>) * 2
/* if start is a Sunday, adjust by -1 */
+ case when datepart(weekday, <start>) = 8 - ##datefirst then -1 else 0 end
/* if end is a Saturday, adjust by -1 */
+ case when datepart(weekday, <end>) = (13 - ##datefirst) % 7 + 1 then -1 else 0 end
datediff(week, ...) always uses a Saturday-to-Sunday boundary for weeks, so that expression is deterministic and doesn't need to be modified (as long as our definition of weekdays is consistently Monday through Friday.) Day numbering does vary according to the ##datefirst setting and the modified calculations handle this correction with the small complication of some modular arithmetic.
A cleaner way to deal with the Saturday/Sunday thing is to translate the dates prior to extracting a day of week value. After shifting, the values will be back in line with a fixed (and probably more familiar) numbering that starts with 1 on Sunday and ends with 7 on Saturday.
datediff(day, <start>, <end>) + 1 - datediff(week, <start>, <end>) * 2
+ case when datepart(weekday, dateadd(day, ##datefirst, <start>)) = 1 then -1 else 0 end
+ case when datepart(weekday, dateadd(day, ##datefirst, <end>)) = 7 then -1 else 0 end
I've tracked this form of the solution back at least as far as 2002 and an Itzik Ben-Gan article. (https://technet.microsoft.com/en-us/library/aa175781(v=sql.80).aspx) Though it needed a small tweak since newer date types don't allow date arithmetic, it is otherwise identical.
EDIT:
I added back the +1 that had somehow been left off. It's also worth noting that this method always counts the start and end days. It also assumes that the end date is on or after the start date.
None of the functions above work for the same week or deal with holidays. I wrote this:
create FUNCTION [dbo].[ShiftHolidayToWorkday](#date date)
RETURNS date
AS
BEGIN
IF DATENAME( dw, #Date ) = 'Saturday'
SET #Date = DATEADD(day, - 1, #Date)
ELSE IF DATENAME( dw, #Date ) = 'Sunday'
SET #Date = DATEADD(day, 1, #Date)
RETURN #date
END
GO
create FUNCTION [dbo].[GetHoliday](#date date)
RETURNS varchar(50)
AS
BEGIN
declare #s varchar(50)
SELECT #s = CASE
WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year] ) + '-01-01') = #date THEN 'New Year'
WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]+1) + '-01-01') = #date THEN 'New Year'
WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year] ) + '-07-04') = #date THEN 'Independence Day'
WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year] ) + '-12-25') = #date THEN 'Christmas Day'
--WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]) + '-12-31') = #date THEN 'New Years Eve'
--WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]) + '-11-11') = #date THEN 'Veteran''s Day'
WHEN [Month] = 1 AND [DayOfMonth] BETWEEN 15 AND 21 AND [DayName] = 'Monday' THEN 'Martin Luther King Day'
WHEN [Month] = 5 AND [DayOfMonth] >= 25 AND [DayName] = 'Monday' THEN 'Memorial Day'
WHEN [Month] = 9 AND [DayOfMonth] <= 7 AND [DayName] = 'Monday' THEN 'Labor Day'
WHEN [Month] = 11 AND [DayOfMonth] BETWEEN 22 AND 28 AND [DayName] = 'Thursday' THEN 'Thanksgiving Day'
WHEN [Month] = 11 AND [DayOfMonth] BETWEEN 23 AND 29 AND [DayName] = 'Friday' THEN 'Day After Thanksgiving'
ELSE NULL END
FROM (
SELECT
[Year] = YEAR(#date),
[Month] = MONTH(#date),
[DayOfMonth] = DAY(#date),
[DayName] = DATENAME(weekday,#date)
) c
RETURN #s
END
GO
create FUNCTION [dbo].GetHolidays(#year int)
RETURNS TABLE
AS
RETURN (
select dt, dbo.GetHoliday(dt) as Holiday
from (
select dateadd(day, number, convert(varchar,#year) + '-01-01') dt
from master..spt_values
where type='p'
) d
where year(dt) = #year and dbo.GetHoliday(dt) is not null
)
create proc UpdateHolidaysTable
as
if not exists(select TABLE_NAME from INFORMATION_SCHEMA.TABLES where TABLE_NAME = 'Holidays')
create table Holidays(dt date primary key clustered, Holiday varchar(50))
declare #year int
set #year = 1990
while #year < year(GetDate()) + 20
begin
insert into Holidays(dt, Holiday)
select a.dt, a.Holiday
from dbo.GetHolidays(#year) a
left join Holidays b on b.dt = a.dt
where b.dt is null
set #year = #year + 1
end
create FUNCTION [dbo].[GetWorkDays](#StartDate DATE = NULL, #EndDate DATE = NULL)
RETURNS INT
AS
BEGIN
IF #StartDate IS NULL OR #EndDate IS NULL
RETURN 0
IF #StartDate >= #EndDate
RETURN 0
DECLARE #Days int
SET #Days = 0
IF year(#StartDate) * 100 + datepart(week, #StartDate) = year(#EndDate) * 100 + datepart(week, #EndDate)
--same week
select #Days = (DATEDIFF(dd, #StartDate, #EndDate))
- (CASE WHEN DATENAME(dw, #StartDate) = 'Sunday' THEN 1 ELSE 0 END)
- (CASE WHEN DATENAME(dw, #EndDate) = 'Saturday' THEN 1 ELSE 0 END)
- (select count(*) from Holidays where dt between #StartDate and #EndDate)
ELSE
--diff weeks
select #Days = (DATEDIFF(dd, #StartDate, #EndDate) + 1)
- (DATEDIFF(wk, #StartDate, #EndDate) * 2)
- (CASE WHEN DATENAME(dw, #StartDate) = 'Sunday' THEN 1 ELSE 0 END)
- (CASE WHEN DATENAME(dw, #EndDate) = 'Saturday' THEN 1 ELSE 0 END)
- (select count(*) from Holidays where dt between #StartDate and #EndDate)
RETURN #Days
END
Using a date table:
DECLARE
#StartDate date = '2014-01-01',
#EndDate date = '2014-01-31';
SELECT
COUNT(*) As NumberOfWeekDays
FROM dbo.Calendar
WHERE CalendarDate BETWEEN #StartDate AND #EndDate
AND IsWorkDay = 1;
If you don't have that, you can use a numbers table:
DECLARE
#StartDate datetime = '2014-01-01',
#EndDate datetime = '2014-01-31';
SELECT
SUM(CASE WHEN DATEPART(dw, DATEADD(dd, Number-1, #StartDate)) BETWEEN 2 AND 6 THEN 1 ELSE 0 END) As NumberOfWeekDays
FROM dbo.Numbers
WHERE Number <= DATEDIFF(dd, #StartDate, #EndDate) + 1 -- Number table starts at 1, we want a 0 base
They should both be fast and it takes out the ambiguity/complexity. The first option is the best but if you don't have a calendar table you can allways create a numbers table with a CTE.
DECLARE #StartDate datetime,#EndDate datetime
select #StartDate='3/2/2010', #EndDate='3/7/2010'
DECLARE #TotalDays INT,#WorkDays INT
DECLARE #ReducedDayswithEndDate INT
DECLARE #WeekPart INT
DECLARE #DatePart INT
SET #TotalDays= DATEDIFF(day, #StartDate, #EndDate) +1
SELECT #ReducedDayswithEndDate = CASE DATENAME(weekday, #EndDate)
WHEN 'Saturday' THEN 1
WHEN 'Sunday' THEN 2
ELSE 0 END
SET #TotalDays=#TotalDays-#ReducedDayswithEndDate
SET #WeekPart=#TotalDays/7;
SET #DatePart=#TotalDays%7;
SET #WorkDays=(#WeekPart*5)+#DatePart
SELECT #WorkDays
CREATE FUNCTION x
(
#StartDate DATETIME,
#EndDate DATETIME
)
RETURNS INT
AS
BEGIN
DECLARE #Teller INT
SET #StartDate = DATEADD(dd,1,#StartDate)
SET #Teller = 0
IF DATEDIFF(dd,#StartDate,#EndDate) <= 0
BEGIN
SET #Teller = 0
END
ELSE
BEGIN
WHILE
DATEDIFF(dd,#StartDate,#EndDate) >= 0
BEGIN
IF DATEPART(dw,#StartDate) < 6
BEGIN
SET #Teller = #Teller + 1
END
SET #StartDate = DATEADD(dd,1,#StartDate)
END
END
RETURN #Teller
END
I took the various examples here, but in my particular situation we have a #PromisedDate for delivery and a #ReceivedDate for the actual receipt of the item. When an item was received before the "PromisedDate" the calculations were not totaling correctly unless I ordered the dates passed into the function by calendar order. Not wanting to check the dates every time, I changed the function to handle this for me.
Create FUNCTION [dbo].[fnGetBusinessDays]
(
#PromiseDate date,
#ReceivedDate date
)
RETURNS integer
AS
BEGIN
DECLARE #days integer
SELECT #days =
Case when #PromiseDate > #ReceivedDate Then
DATEDIFF(d,#PromiseDate,#ReceivedDate) +
ABS(DATEDIFF(wk,#PromiseDate,#ReceivedDate)) * 2 +
CASE
WHEN DATENAME(dw, #PromiseDate) <> 'Saturday' AND DATENAME(dw, #ReceivedDate) = 'Saturday' THEN 1
WHEN DATENAME(dw, #PromiseDate) = 'Saturday' AND DATENAME(dw, #ReceivedDate) <> 'Saturday' THEN -1
ELSE 0
END +
(Select COUNT(*) FROM CompanyHolidays
WHERE HolidayDate BETWEEN #ReceivedDate AND #PromiseDate
AND DATENAME(dw, HolidayDate) <> 'Saturday' AND DATENAME(dw, HolidayDate) <> 'Sunday')
Else
DATEDIFF(d,#PromiseDate,#ReceivedDate) -
ABS(DATEDIFF(wk,#PromiseDate,#ReceivedDate)) * 2 -
CASE
WHEN DATENAME(dw, #PromiseDate) <> 'Saturday' AND DATENAME(dw, #ReceivedDate) = 'Saturday' THEN 1
WHEN DATENAME(dw, #PromiseDate) = 'Saturday' AND DATENAME(dw, #ReceivedDate) <> 'Saturday' THEN -1
ELSE 0
END -
(Select COUNT(*) FROM CompanyHolidays
WHERE HolidayDate BETWEEN #PromiseDate and #ReceivedDate
AND DATENAME(dw, HolidayDate) <> 'Saturday' AND DATENAME(dw, HolidayDate) <> 'Sunday')
End
RETURN (#days)
END
If you need to add work days to a given date, you can create a function that depends on a calendar table, described below:
CREATE TABLE Calendar
(
dt SMALLDATETIME PRIMARY KEY,
IsWorkDay BIT
);
--fill the rows with normal days, weekends and holidays.
create function AddWorkingDays (#initialDate smalldatetime, #numberOfDays int)
returns smalldatetime as
begin
declare #result smalldatetime
set #result =
(
select t.dt from
(
select dt, ROW_NUMBER() over (order by dt) as daysAhead from calendar
where dt > #initialDate
and IsWorkDay = 1
) t
where t.daysAhead = #numberOfDays
)
return #result
end
As with DATEDIFF, I do not consider the end date to be part of the interval.
The number of (for example) Sundays between #StartDate and #EndDate is the number of Sundays between an "initial" Monday and the #EndDate minus the number of Sundays between this "initial" Monday and the #StartDate. Knowing this, we can calculate the number of workdays as follows:
DECLARE #StartDate DATETIME
DECLARE #EndDate DATETIME
SET #StartDate = '2018/01/01'
SET #EndDate = '2019/01/01'
SELECT DATEDIFF(Day, #StartDate, #EndDate) -- Total Days
- (DATEDIFF(Day, 0, #EndDate)/7 - DATEDIFF(Day, 0, #StartDate)/7) -- Sundays
- (DATEDIFF(Day, -1, #EndDate)/7 - DATEDIFF(Day, -1, #StartDate)/7) -- Saturdays
Best regards!
I borrowed some ideas from others to create my solution. I use inline code to ignore weekends and U.S. federal holidays. In my environment, EndDate may be null, but it will never precede StartDate.
CREATE FUNCTION dbo.ufn_CalculateBusinessDays(
#StartDate DATE,
#EndDate DATE = NULL)
RETURNS INT
AS
BEGIN
DECLARE #TotalBusinessDays INT = 0;
DECLARE #TestDate DATE = #StartDate;
IF #EndDate IS NULL
RETURN NULL;
WHILE #TestDate < #EndDate
BEGIN
DECLARE #Month INT = DATEPART(MM, #TestDate);
DECLARE #Day INT = DATEPART(DD, #TestDate);
DECLARE #DayOfWeek INT = DATEPART(WEEKDAY, #TestDate) - 1; --Monday = 1, Tuesday = 2, etc.
DECLARE #DayOccurrence INT = (#Day - 1) / 7 + 1; --Nth day of month (3rd Monday, for example)
--Increment business day counter if not a weekend or holiday
SELECT #TotalBusinessDays += (
SELECT CASE
--Saturday OR Sunday
WHEN #DayOfWeek IN (6,7) THEN 0
--New Year's Day
WHEN #Month = 1 AND #Day = 1 THEN 0
--MLK Jr. Day
WHEN #Month = 1 AND #DayOfWeek = 1 AND #DayOccurrence = 3 THEN 0
--G. Washington's Birthday
WHEN #Month = 2 AND #DayOfWeek = 1 AND #DayOccurrence = 3 THEN 0
--Memorial Day
WHEN #Month = 5 AND #DayOfWeek = 1 AND #Day BETWEEN 25 AND 31 THEN 0
--Independence Day
WHEN #Month = 7 AND #Day = 4 THEN 0
--Labor Day
WHEN #Month = 9 AND #DayOfWeek = 1 AND #DayOccurrence = 1 THEN 0
--Columbus Day
WHEN #Month = 10 AND #DayOfWeek = 1 AND #DayOccurrence = 2 THEN 0
--Veterans Day
WHEN #Month = 11 AND #Day = 11 THEN 0
--Thanksgiving
WHEN #Month = 11 AND #DayOfWeek = 4 AND #DayOccurrence = 4 THEN 0
--Christmas
WHEN #Month = 12 AND #Day = 25 THEN 0
ELSE 1
END AS Result);
SET #TestDate = DATEADD(dd, 1, #TestDate);
END
RETURN #TotalBusinessDays;
END
That's working for me, in my country on Saturday and Sunday are non-working days.
For me is important the time of #StartDate and #EndDate.
CREATE FUNCTION [dbo].[fnGetCountWorkingBusinessDays]
(
#StartDate as DATETIME,
#EndDate as DATETIME
)
RETURNS INT
AS
BEGIN
DECLARE #res int
SET #StartDate = CASE
WHEN DATENAME(dw, #StartDate) = 'Saturday' THEN DATEADD(dd, 2, DATEDIFF(dd, 0, #StartDate))
WHEN DATENAME(dw, #StartDate) = 'Sunday' THEN DATEADD(dd, 1, DATEDIFF(dd, 0, #StartDate))
ELSE #StartDate END
SET #EndDate = CASE
WHEN DATENAME(dw, #EndDate) = 'Saturday' THEN DATEADD(dd, 0, DATEDIFF(dd, 0, #EndDate))
WHEN DATENAME(dw, #EndDate) = 'Sunday' THEN DATEADD(dd, -1, DATEDIFF(dd, 0, #EndDate))
ELSE #EndDate END
SET #res =
(DATEDIFF(hour, #StartDate, #EndDate) / 24)
- (DATEDIFF(wk, #StartDate, #EndDate) * 2)
SET #res = CASE WHEN #res < 0 THEN 0 ELSE #res END
RETURN #res
END
GO
Create function like:
CREATE FUNCTION dbo.fn_WorkDays(#StartDate DATETIME, #EndDate DATETIME= NULL )
RETURNS INT
AS
BEGIN
DECLARE #Days int
SET #Days = 0
IF #EndDate = NULL
SET #EndDate = EOMONTH(#StartDate) --last date of the month
WHILE DATEDIFF(dd,#StartDate,#EndDate) >= 0
BEGIN
IF DATENAME(dw, #StartDate) <> 'Saturday'
and DATENAME(dw, #StartDate) <> 'Sunday'
and Not ((Day(#StartDate) = 1 And Month(#StartDate) = 1)) --New Year's Day.
and Not ((Day(#StartDate) = 4 And Month(#StartDate) = 7)) --Independence Day.
BEGIN
SET #Days = #Days + 1
END
SET #StartDate = DATEADD(dd,1,#StartDate)
END
RETURN #Days
END
You can call the function like:
select dbo.fn_WorkDays('1/1/2016', '9/25/2016')
Or like:
select dbo.fn_WorkDays(StartDate, EndDate)
from table1
Create Function dbo.DateDiff_WeekDays
(
#StartDate DateTime,
#EndDate DateTime
)
Returns Int
As
Begin
Declare #Result Int = 0
While #StartDate <= #EndDate
Begin
If DateName(DW, #StartDate) not in ('Saturday','Sunday')
Begin
Set #Result = #Result +1
End
Set #StartDate = DateAdd(Day, +1, #StartDate)
End
Return #Result
End
I found the below TSQL a fairly elegant solution (I don't have permissions to run functions). I found the DATEDIFF ignores DATEFIRST and I wanted my first day of the week to be a Monday. I also wanted the first working day to be set a zero and if it falls on a weekend Monday will be a zero. This may help someone who has a slightly different requirement :)
It does not handle bank holidays
SET DATEFIRST 1
SELECT
,(DATEDIFF(DD, [StartDate], [EndDate]))
-(DATEDIFF(wk, [StartDate], [EndDate]))
-(DATEDIFF(wk, DATEADD(dd,-##DATEFIRST,[StartDate]), DATEADD(dd,-##DATEFIRST,[EndDate]))) AS [WorkingDays]
FROM /*Your Table*/
One approach is to 'walk the dates' from start to finish in conjunction with a case expression which checks if the day is not a Saturday or a Sunday and flagging it(1 for weekday, 0 for weekend). And in the end just sum flags(it would be equal to the count of 1-flags as the other flag is 0) to give you the number of weekdays.
You can use a GetNums(startNumber,endNumber) type of utility function which generates a series of numbers for 'looping' from start date to end date. Refer http://tsql.solidq.com/SourceCodes/GetNums.txt for an implementation. The logic can also be extended to cater for holidays(say if you have a holidays table)
declare #date1 as datetime = '19900101'
declare #date2 as datetime = '19900120'
select sum(case when DATENAME(DW,currentDate) not in ('Saturday', 'Sunday') then 1 else 0 end) as noOfWorkDays
from dbo.GetNums(0,DATEDIFF(day,#date1, #date2)-1) as Num
cross apply (select DATEADD(day,n,#date1)) as Dates(currentDate)