I want to terminate a job after running until a particular time, but I should not specify a date.
I know sendevent -E KILLJOB -J job name -T "mm/dd/yy HH:mm, but this has a date also to be specified. But for my requirement, I don't need a date. Can someone help me how to achieve this?
Thanks,
Hema
If sendevent is being as command attribute for a CMD job type.
The owner must have access to the Autosys DB and not just to regular machine where jobs run.
Please check the machine / owner privilages to do so.
The other way through autosys attributes.
Consider the job starts at HH:mm hour of the day.
Then the minutes between HH:mm and 02:00 to be assigned for term_run_time attribute in the job.
Once the job starts, it would terminate after those minutes if not completed.
Example:
Job start time is 16:00
Between 16:00 and 02:00 there are 10 hours = 600 minutes
term_run_time: 600
This 600 minutes is relative to starting time.
In autosys there is no attribute to terminate a job at an absolute time.
Hope this helps
Related
I have a pipeline in which ingest data from an API and load them into an azure database. The pipeline is called by a trigger. The load time is normally 6 to 7 hours. But sometimes for some reason, the pipeline runs more than 24 hours and on the next day again is executed by the trigger. So I want to stop the pipeline, if pipeline it runs more than 24 hours. Appreciate any help.
In Azure Pipeline, set Timeout for agent job would achieve your demand. Each job has a timeout. If the job has not completed in the specified time, the server will cancel the job. It will attempt to signal the agent to stop, and it will mark the job as canceled: https://learn.microsoft.com/en-us/azure/devops/pipelines/process/runs?view=azure-devops#timeouts-and-disconnects
Set 1440 minutes for 24 hours.
I have an SSIS job that runs every 15 minutes. One of over 2 dozen that run on regular intervals throughout the day. Occasionally, they fail, the job fails before ever getting to the point where it executes the SSIS package. You can see below. I've attached an image of the report ssis execution. 3PM today it failed, going into the SSIS Report Execution, no entry was there for 3PM.
How do I debug this? It seems to happen in spurts. When 1 fails, all of a sudden 5 will fail at the same interval. They may pick up and run fine the next time, they may fail again.
JOB RUN: 'Production_365_To_DW_Full_Sync' was run on 9/9/2020 at 3:00:00 PM
DURATION: 0 hours, 0 minutes, 20 seconds
STATUS: Failed
MESSAGES: The job failed. The Job was invoked by Schedule 29 (Every 30 Minutes). The last step to run was step 1 (Execute SSIS).
I have a query which will run if I simply run it through console or from code.
When I created Scheduled Query for the Query, it would not run. The Scheduled Query is successfully created, and the interval I set (every 2 hours) is correctly implemented but only the jobs are not created (I can see in Scheduled query that the time to run is being incremented by 2 hours every time it is supposed to run).
These are the properties when running query from Scheduled query:
Overwrite table, Processing location: US, Allow large results, Batch priority
If I do a Schedule Backfill, it creates 12 jobs which fails with an error messages similar to the following:
Exceeded CPU limit 125%
Exceeded memory
If I cancel all the created jobs and leave one to run, it would run successfully. The Scheduled Query itself would not create any jobs.
I started the Scheduled query at 12:00 and made it to run for every 2 hours in repeats.
I assumed the jobs would run at the start time but apparently it is not the case. Scheduled Query ran perfectly as intended from 14:00 following with 16:00 and so on.
The errors regarding maximum CPU/memory usage is because the query I wrote had ORDER BY statement which was causing this issue. Removing that cleared the issue.
I am facing issue with sql agent , on changing the server date it does not start at its schedule time while job is schedule daily at fixed time. No logs are found on this . This issue also occurs while system date has been changed to its real date . I have to restart the sql agent after that to invoke the job at its schedule time.
SQL Agent scheduled jobs will have last run date/time and next run date/time. Each time the jobs run, these values get updated. Please look in MSDB and you will see these details. You can also look in Job history.
When you manually reset the system clock to a date later than now, then your next run date/time will be in the past. As you have mentioned, bouncing the agent service should start the jobs again.
Raj
I am using the amazonaws es3 server.I want to schedule my cron with command line.
I am using the this command for scheduling the cron job
at -f shellscript.sh -v 18:30
but it will schedule for only one time i want to configure manually like once a day or every five minutes .
Please help with command which command i have to used
Thnaks,
As #The.Anti.9 noted, this kind of question fits in Serverfault.
To answer your question, crontab is a little more powerful than 'at' and gives you more flexibility as you can run the job repeatedly for instance daily, weekly, monthly.
For instance for your example, if you need to run the script every day at 18:30 you'd do this,
$ crontab -e
then add the following
30 18 * * * /path/to/your/script.sh
save and you are done.
Note: 30 18 indicates time 18:30, and *s indicate that it should run every day of every month) If you need to run it on a particular day of the month just check it out on the man page of crontab.
Doesn't crontab -e work?
and to generate crontab code http://www.openjs.com/scripts/jslibrary/demos/crontab.php should help.