Okay, so I've done quite a lot of reading on the possibility of emulating the networkdays function of excel in sql, and have come to the conclusion that by far the easiest solution is to have a calendar table which will flag working days or non working days. However, due to circumstances out of my control, we don't have access to such a luxury and it's unlikely that we will any time in the near future.
Currently I have managed to bodge together what is undoubtedly a horrible ineffecient query in SQL that does work - the catch is, it will only work for a single client record at a time.
SELECT O_ASSESSMENTS.ASM_ID,
O_ASSESSMENTS.ASM_START_DATE,
O_ASSESSMENTS.ASM_END_DATE,
sum(CASE
When TO_CHAR(O_ASSESSMENTS.ASM_START_DATE + rownum -1,'Day')
= 'Sunday ' THEN 0
When TO_CHAR(O_ASSESSMENTS.ASM_START_DATE + rownum -1,'Day')
= 'Saturday ' THEN 0
WHEN O_ASSESSMENTS.ASM_START_DATE + rownum - 1
IN ('03-01-2000','21-04-2000','24-04-2000','01-05-2000','29-05-2000','28-08-2000','25-12-2000','26-12-2000','01-01-2001','13-04-2001','16-04-2001','07-05-2001','28-05-2001','27-08-2001','25-12-2001','26-12-2001','01-01-2002','29-03-2002','01-04-2002','06-04-2002','03-06-2002','04-06-2002','26-08-2002','25-12-2002','26-12-2002','01-01-2003','18-04-2003','21-04-2003','05-05-2003','26-05-2003','25-08-2003','25-12-2003','26-12-2003','01-01-2004','09-04-2004','12-04-2004','03-05-2004','31-05-2004','30-08-2004','25-12-2004','26-12-2004','27-12-2004','28-12-2004','01-01-2005','03-01-2005','25-03-2005','28-03-2005','02-05-2005','30-05-2005','29-08-2005','27-12-2005','28-12-2005','02-01-2006','14-04-2006','17-04-2006','01-05-2006','29-05-2006','28-08-2006','25-12-2006','26-12-2006','02-01-2007','06-04-2007','09-04-2007','07-05-2007','28-05-2007','27-08-2007','25-12-2007','26-12-2007','01-01-2008','21-03-2008','24-03-2008','05-05-2008','26-05-2008','25-08-2008','25-12-2008','26-12-2008','01-01-2009','10-04-2009','13-04-2009','04-05-2009','25-05-2009','31-08-2009','25-12-2009','28-12-2009','01-01-2010','02-04-2010','05-04-2010','03-05-2010','31-05-2010','30-08-2010','24-12-2010','27-12-2010','28-12-2010','31-12-2010','03-01-2011','22-04-2011','25-04-2011','29-04-2011','02-05-2011','30-05-2011','29-08-2011','26-12-2011','27-12-2011')
THEN 0
ELSE 1
END)-1 AS Week_Day
From O_ASSESSMENTS,
ALL_OBJECTS
WHERE O_ASSESSMENTS.ASM_QSA_ID IN ('TYPE1')
AND O_ASSESSMENTS.ASM_END_DATE >= '01/01/2012'
AND O_ASSESSMENTS.ASM_ID = 'A00000'
AND ROWNUM <= O_ASSESSMENTS.ASM_END_DATE-O_ASSESSMENTS.ASM_START_DATE+1
GROUP BY
O_ASSESSMENTS.ASM_ID,
O_ASSESSMENTS.ASM_START_DATE,
O_ASSESSMENTS.ASM_END_DATE
Basically, I'm wondering if a) I should stop wasting my time on this or b) is it possible to get this to work for multiple clients? Any pointers appreciated thanks!
Edit: Further clarification - I already work out timescales using excel, but it would be ideal if we could do it in the report as the report in question is something that we would like end users to be able to run without any further manipulation.
Edit:
MarkBannister's answer works perfectly albeit slowly (though I had expected as much given it's not the preferred solution) - the challenge now lies in me integrating this into an existing report!
with
calendar_cte as (select
to_date('01-01-2000')+level-1 calendar_date,
case when to_char(to_date('01-01-2000')+level-1, 'day') in ('sunday ','saturday ') then 0 when to_date('01-01-2000')+level-1 in ('03-01-2000','21-04-2000','24-04-2000','01-05-2000','29-05-2000','28-08-2000','25-12-2000','26-12-2000','01-01-2001','13-04-2001','16-04-2001','07-05-2001','28-05-2001','27-08-2001','25-12-2001','26-12-2001','01-01-2002','29-03-2002','01-04-2002','06-04-2002','03-06-2002','04-06-2002','26-08-2002','25-12-2002','26-12-2002','01-01-2003','18-04-2003','21-04-2003','05-05-2003','26-05-2003','25-08-2003','25-12-2003','26-12-2003','01-01-2004','09-04-2004','12-04-2004','03-05-2004','31-05-2004','30-08-2004','25-12-2004','26-12-2004','27-12-2004','28-12-2004','01-01-2005','03-01-2005','25-03-2005','28-03-2005','02-05-2005','30-05-2005','29-08-2005','27-12-2005','28-12-2005','02-01-2006','14-04-2006','17-04-2006','01-05-2006','29-05-2006','28-08-2006','25-12-2006','26-12-2006','02-01-2007','06-04-2007','09-04-2007','07-05-2007','28-05-2007','27-08-2007','25-12-2007','26-12-2007','01-01-2008','21-03-2008','24-03-2008','05-05-2008','26-05-2008','25-08-2008','25-12-2008','26-12-2008','01-01-2009','10-04-2009','13-04-2009','04-05-2009','25-05-2009','31-08-2009','25-12-2009','28-12-2009','01-01-2010','02-04-2010','05-04-2010','03-05-2010','31-05-2010','30-08-2010','24-12-2010','27-12-2010','28-12-2010','31-12-2010','03-01-2011','22-04-2011','25-04-2011','29-04-2011','02-05-2011','30-05-2011','29-08-2011','26-12-2011','27-12-2011','01-01-2012','02-01-2012') then 0 else 1 end working_day
from dual
connect by level <= 1825 + sysdate - to_date('01-01-2000') )
SELECT
a.ASM_ID,
a.ASM_START_DATE,
a.ASM_END_DATE,
sum(c.working_day)-1 AS Week_Day
From
O_ASSESSMENTS a
join calendar_cte c
on c.calendar_date between a.ASM_START_DATE and a.ASM_END_DATE
WHERE a.ASM_QSA_ID IN ('TYPE1')
and a.ASM_END_DATE >= '01/01/2012'
GROUP BY
a.ASM_ID,
a.ASM_START_DATE,
a.ASM_END_DATE

There are a few ways to do this. Perhaps the simplest might be to create a CTE that produces a virtual calendar table, based on Oracle's connect by syntax, and then join it to the Assesments table, like so:
with calendar_cte as (
select to_date('01-01-2000')+level-1 calendar_date,
case when to_char(to_date('01-01-2000')+level-1, 'Day')
in ('Sunday ','Saturday ') then 0
when to_date('01-01-2000')+level-1
in ('03-01-2000','21-04-2000','24-04-2000','01-05-2000','29-05-2000','28-08-2000','25-12-2000','26-12-2000','01-01-2001','13-04-2001','16-04-2001','07-05-2001','28-05-2001','27-08-2001','25-12-2001','26-12-2001','01-01-2002','29-03-2002','01-04-2002','06-04-2002','03-06-2002','04-06-2002','26-08-2002','25-12-2002','26-12-2002','01-01-2003','18-04-2003','21-04-2003','05-05-2003','26-05-2003','25-08-2003','25-12-2003','26-12-2003','01-01-2004','09-04-2004','12-04-2004','03-05-2004','31-05-2004','30-08-2004','25-12-2004','26-12-2004','27-12-2004','28-12-2004','01-01-2005','03-01-2005','25-03-2005','28-03-2005','02-05-2005','30-05-2005','29-08-2005','27-12-2005','28-12-2005','02-01-2006','14-04-2006','17-04-2006','01-05-2006','29-05-2006','28-08-2006','25-12-2006','26-12-2006','02-01-2007','06-04-2007','09-04-2007','07-05-2007','28-05-2007','27-08-2007','25-12-2007','26-12-2007','01-01-2008','21-03-2008','24-03-2008','05-05-2008','26-05-2008','25-08-2008','25-12-2008','26-12-2008','01-01-2009','10-04-2009','13-04-2009','04-05-2009','25-05-2009','31-08-2009','25-12-2009','28-12-2009','01-01-2010','02-04-2010','05-04-2010','03-05-2010','31-05-2010','30-08-2010','24-12-2010','27-12-2010','28-12-2010','31-12-2010','03-01-2011','22-04-2011','25-04-2011','29-04-2011','02-05-2011','30-05-2011','29-08-2011','26-12-2011','27-12-2011')
then 0
else 1
end working_day
from dual
connect by level <= 36525 + sysdate - to_date('01-01-2000') )
SELECT a.ASM_ID,
a.ASM_START_DATE,
a.ASM_END_DATE,
sum(c.working_day) AS Week_Day
From O_ASSESSMENTS a
join calendar_cte c
on c.calendar_date between a.ASM_START_DATE and a.ASM_END_DATE
WHERE a.ASM_QSA_ID IN ('TYPE1') and
a.ASM_END_DATE >= '01/01/2012' -- and a.ASM_ID = 'A00000'
GROUP BY
a.ASM_ID,
a.ASM_START_DATE,
a.ASM_END_DATE
This will produce a virtual table populated with dates from 01 January 2000 to 10 years after the current date, with all weekends marked as non-working days and all days specified in the second in clause (ie. up to 27 December 2011) also marked as non-working days.
The drawback of this method (or any method where the holiday dates are hardcoded into the query) is that each time new holiday dates are defined, every single query that uses this approach will have to have those dates added.

If you can't use a calendar table in Oracle, you might be better off exporting to Excel. Brute force always works.
Networkdays() "returns the number of whole working days between start_date and end_date. Working days exclude weekends and any dates identified in holidays."
Excluding weekends seems fairly straightforward. Every 7-day period will contain two weekend days. You'll just need to take some care with the leftover days.
Holidays are a different story. You have to either store them or pass them as an argument. If you could store them, you'd store them in a calendar table, and your problem would be over. But you can't do that.
So you're looking at passing them as an argument. Off the top of my head--and I haven't had any tea yet this morning--I'd consider a common table expression or a wrapper for a stored procedure.

Related

If statement in a WHERE clause for between two dates

I have a script that counts the number of doses a client has had between their start date and 180 days out.
Now i am trying to have some form of an IF (or CASE) statement in the where clause so its either between the first date and 180 days out OR if that 180 days exceeds 6/30/20, then just do the count between start date and 6/30/20.
In my research i couldnt find anything about using an IF else (or CASE) with dates, in the WHERE function.
This is my current script in SQL Server
SELECT
t.clinic,
t.display_id,
m.FirstDate,
DATEADD(DAY,180,MIN(take_on_date)) AS Days_180,
COUNT(t.dose_number) AS Doses
FROM (SELECT CLINIC
, display_id
, MIN(TAKE_ON_DATE) AS FirstDate
FROM factMedHist
GROUP BY Clinic, display_id
) AS m
INNER JOIN factMedHist AS t
ON t.Clinic = m.Clinic
AND t.display_id = m.display_id
WHERE t.take_on_date
BETWEEN m.FirstDate AND DATEADD(DAY,180,m.FirstDate)
GROUP BY t.Clinic, t.display_id,m.FirstDate
So "start date" = "FirstDate" = "min(TAKE_ON_DATE)". And "Client" = "display_id" but you group and join on the tuple <display_id, Clinic>. I see many struggles in the future based on this unfortunately common issue. Consistent terminology is important.
So here is one take on your issue. A bit verbose to demonstrate what it does. Note also the provision of a MVCE - something that you should provide to encourage others to help. It is a bit of effort you should not expect others to take on just to solve your issues.
You were on the correct path with CASE - but lost it when you started thinking of it as a control-of-flow construct as it is in most other languages. You can compute the startdate and enddate for each client (clinic, display_id)
with cte as (select *,
min(takedate) over (partition by display_id, clinic order by takedate) as startdate,
dateadd(day, 180, min(takedate) over (partition by display_id, clinic order by takedate)) as enddate
from #medhist
)
You were doing that - but the problem is that you need reference that end date in the where clause to filter the rows as desired. Like this:
where takedate <= case when enddate <= '20200630' then enddate else '20200630' end
Fiddle here. Notice that the first take date is irrelevant in the where clause. This is one way to achieve your result. Another obvious approach is to use a conditional sum. That would be good practice if you wanted to increase your knowledge. Depending on your situation one might be more efficient than the other. CTEs are just syntactic sugar but do allow the building of logic in a piece-by-piece approach - something I find can be very helpful in developing a completed tsql statement.
WHERE t.take_on_date BETWEEN m.FirstDate AND DATEADD(DAY,180,m.FirstDate)
OR t.take_on_date > DATEADD(DAY, 180, '20200630')

adding business days in oracle sql

I have two date fields, DATE_FIELD_ONE = 8/30/2018 and DATE_FIELD_TWO = DATE_FIELD_ONE + 20. I need to find what DATE_FIELD_TWO should be if I'm only added 20 business days . How would I accomplish this? I thought maybe trying 'DY' but not sure how to get it to work. Thanks.
CASE WHEN TO_CHAR(TO_DATE(DATE_FIELD_ONE),'DY')='SAT' THEN 1 ELSE 0 END
CASE WHEN TO_CHAR(TO_DATE(DATE_FIELD_ONE),'DY')='SUN' THEN 1 ELSE 0 END
You may try this :
select max(date_field_two) as date_field_two
from
(
select date'2018-08-30'+
cast(case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH')
in ('6','7') then
0
else
level
end as int) as date_field_two,
sum(cast(case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH')
in ('6','7') then
0
else
1
end as int)) over (order by level) as next_day
from dual
connect by level <= 20*1.5
-- 20 is the day to be added, every time 5(#of business days)*1.5 > 7(#of week days)
-- 7=5+2<5+(5/2)=5*(1+1/2)=5*1.5 [where 1.5 is just a coefficient might be replaced a greater one like 2]
-- so 4*5*1.5=20*1.5 > 4*7
)
where next_day = 20;
DATE_FIELD_TWO
-----------------
27.09.2018
by using connect by dual clause.
P.S. Ignored the case for public holidays, which differ from one culture to another , depending on the question being related with only weekends.
Rextester Demo
Edit : Assume you have a national holidays on '2018-09-25' and '2018-09-26' (in this set of days), then consider the following :
select max(date_field_two) as date_field_two
from
(
select date'2018-08-30'+
(case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH')
in ('6','7') then
0
when date'2018-08-30'+level in (date'2018-09-25',date'2018-09-26') then
0
else
level
end) as date_field_two,
sum(cast(case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH')
in ('6','7') then
0
when date'2018-08-30'+level in (date'2018-09-25',date'2018-09-26') then
0
else
1
end as int)) over (order by level) as next_day
from dual
connect by level <= 20*2
)
where next_day = 20;
DATE_FIELD_TWO
-----------------
01.10.2018
which iterates one day next, as in this case, unless this holiday coincides with weekend.
you can define workdays to be whatever you like if you use a PL/SQL function
Have a simple prototype here - without any holidays - but it could be adapted for that purpose using the same kind of logic.
create or replace function add_business_days (from_date IN date, bd IN integer) return date as
fd date := trunc(from_date,'iw');
cnt int := (from_date-fd)+bd-1;
ww int := ceil(cnt/5);
wd int := mod(cnt,5);
begin
return from_date + (ww*7)+wd;
end;
/
I realize you already have an answer, but for what it's worth this is something we deal with all the time and have what has turned out to be a very good solution.
In effect, we maintain a separate table called "work days" that has every conceivable date we would ever compare (and that definition will vary from application to application, of course -- but in any case it will never be "huge" by RDBMS standards). There is a boolean flag that dictates if the date is a work day or a weekend/holiday, but more importantly there is an index value that only increments on work days. The table looks like this:
The advantage to this is transparency and scalability. If you want the difference between two dates in work days:
select
h.entry_date, h.invoice_date, wd2.workday_index - wd1.workday_index as delta
from
sales_order_data h
join util.work_days wd1 on h.sales_order_entry_dte = wd1.cal_date
join util.work_days wd2 on h.invoice_dte = wd2.cal_date
If you need to take a date in a table and add 20 days (like your original problem statement):
select
h.date_field_1, wd2.cal_date as date_field_1_plus_20
from
my_table h
join util.work_days wd1 on h.date_field_1 = wd1.cal_date
join util.work_days wd2 on
wd1.workday_index + 20 = wd2.workday_index and
wd2.is_workday
(disclaimer, this is in PostgreSQL, which is why I have the boolean. In Oracle, I'm guessing you need to change that to an integer and say =1)
Also, for the bonus question, this also gives two different options for defining "work day," one that rolls forward and another that rolls backwards (hence the workday_index and workday_index_back). For example, if you need something on a Saturday, and Saturday is not a work day, that means you need it on Friday. Conversely, if something is to be delivered on Saturday, and Saturday is not on a work day, then that means it will be available on Monday. The context of how to handle non-workdays differs, and this method affords you the option of chosing the right one.
As a final selling point, this option allows you to define holidays as non-work days also... and you can do this or not do this; it's up to you. The solution permits either option. You could theoretically add two more columns for work day index weekend only that gave you both options.

Trying to exclude a subset within a few days of a report

I am trying to exclude trades of a certain typology if they are less than 4 days but this filter im using is super slow in returning results. it also doesnt capture trades which are booked 10th of may expiring 13th june which it should. if I amend it to include these it will also include trades within the same month less than 4 days. can someone help me make it more efficient and capturing what I want. using orcale sql developer
and ( DC.M_TYPOLOGY <> 'Repo BD' OR (DC.M_TYPOLOGY ='Repo BD' and
(((to_char( DC.M_OPTMAT , 'YYYY')- to_char (DC.M_TRADEDATE, 'YYYY'))= 0
and (to_char( DC.M_OPTMAT , 'MM')- to_char (DC.M_TRADEDATE, 'MM') < 1))
and (to_char( DC.M_OPTMAT , 'DD')- to_char (DC.M_TRADEDATE, 'DD') > 4))))
All that conversion is unnecessary (and wrong - what happens when trades span year end?). We can do arithmetic with Oracle dates so this is the same:
( DC.M_TYPOLOGY <> 'Repo BD'
OR (DC.M_TYPOLOGY ='Repo BD'
and DC.M_TRADEDATE - DC.M_OPTMAT < 4 )
)
Note: this answer posted before the recent edit to the question. I'm leaving this in place but I will revise it once the OP has clarified the rules they want to enforce.
Of course, this may not speed your query up. Performance problems can arise from many different causes and there simply isn't enough detail provided.

Historical Backlog Using Oracle SQL

I'm trying to develop a query that will show the historical backlog, month by month for applications my organization processes.
The table I'm querying has each row represent an application.
This is fairly simple for a single month by taking into account when the application was created and when it was closed. I can use the code below.
SELECT COUNT(*)
FROM APPLICATIONS
WHERE TRUNC(CRTE_DTE,'mm') <= TO_DATE('09/01/2016','mm/dd/yyyy')
AND (TRUNC(CLOS_DTE,'mm')> TO_DATE('09/01/2016','mm/dd/yyyy') OR CLOS_DTE IS
NULL)
;
What I would like to do, is create something like this but grouped by month.
i.e. with output that looks similar to:
January 250
February 350
March 290
etc.
For my purposes, I'm defining backlog as any application that hadn't yet been closed by the time that month had ended while excluding any applications opened after that month had ended.
I don't have access to run PL/SQL, but if that's a requirement please let me know.
First time posting here, so if I didn't explain something correctly, let me know!
Try something like this:
SELECT d.dt, COUNT(*)
FROM
APPLICATIONS a,
(SELECT ADD_MONTHS(:DATE1, ROWNUM-1) DT FROM DUAL CONNECT BY ROWNUM<=MONTHS_BETWEEN(:DATE2, :DATE1)+1) d
WHERE TRUNC(a.CRTE_DTE,'mm') <= d.dt
AND (TRUNC(a.CLOS_DTE,'mm')> d.dt OR CLOS_DTE IS NULL)
GROUP BY D.DT
:date1 - start date, for example 08/01/2016, :date2 - end date, for example 10/01/2016, in subquery we get row for each month between :date1 and :date2, and then count backlog for them.

SQLl create table /w select statements and defined date ranges

I'm trying to track down new id numbers over time for at least the past twelve months. Note, the data is such that once id numbers are in, they stick around for at least 3-5 years. And I just literally run this thing once a month. These are the specs, Oracle Database 11g Release 11.2.0.3.0 - 64bit Production
PL/SQL Release 11.2.0.3.0 - Production.
So far I'm wondering if I can use more dynamic date ranges and run this whole thing on a timer, or if this is the best way to write something. I've just picked up sql mostly through Googling and looking at sample queries that others have graciously shared. I also do not know how to write PL/SQL right now either but am willing to learn.
create table New_ids_calendar_year_20xx
as
select b.id_num, (bunch of other fields)
from (select * from source_table where date = last_day(date_add(sysdate,-11))a, (select * from source_table where date = last_day(date_add(sysdate,-10))b where a.id_num (+) = b.id_num
union all
*repeats this same select statement /w union all until:
last_day(date_add(sysdate,0)
In Oracle there is no built-in function date_add, maybe you have some which you created, anyway for adding and substracting dates
I used simple sysdate+number. Also I am not quite sure about logic behind your whole query. And for field names - better avoid
reserved words like date in column names, so I used
tdate here.
This query does what your unioned query did for last 30 days. For other periods change 30 to something other.
The whole solution is based on the hierarchical
subquery connect by which gives simple list of numbers 0..29.
select b.id_num, b.field1 field1_b, a.field1 field1_a --..., (bunch of other fields)
from (select level - 1 lvl from dual connect by level <= 30) l
join source_table b
on b.tdate = last_day(trunc(sysdate) - l.lvl - 1)
left join source_table a
on a.id_num = b.id_num and a.tdate = last_day(trunc(sysdate) - l.lvl)
order by lvl desc
For date column you may want to use trunc(tdate) if you store time also, but this way your index on date field will not work if one exists.
In this case change date condition to something like x-1 <= date and date < x.