I need to copy a pf-status of a report. But the programs I want to copy from one to another are in different systems.
Is there any way like download - upload pf-status or something like that ?
Thanks.

What you want to do is to transport the program from one system to the other one. Mainly it depends on your authorizations in both systems and on the settings of landscape, but in case you are authorized and the systems are both in the same transport domain, you can do the following (I do that kind of stuff every day):
On source system
start transaction SE09
create Transport of copies, specify proper target system
include your report there; the entry will be R3TR PROG <name of your program>
release Transport of copies
On target system
start transaction STMS
go to the list of systems (little icon with Truck)
pick the target system there
you get the list of the transports ready for import
click refresh and your transport should show at the bottom of the list
point a cursor on it and trigger the transport
if everything goes right, your entire report is now in target system

You could try SAPLink. It does require that you install SAPLink on both ABAP systems, but after that transferring objects from one to the other is much simpler.
The other option would be to enlist the help of a Basis person, create a transport and have them import it to the target system. But generally, that is not likely to happen.

Related

Best way to export data from other company's SAP

I need to extract some data from my client's SAP ECC (the SUIM -> Users by Complex Selection Criteria -program RSUSR002)
Normally I give them a table of values that I they have to fill some field to extract what I need.
They have to make 63 different extractions (with different values of objects, for example - but inside the same transaction - you can see in the print) from their SAP, to later send to me all extracted files.
Do you know if there is an automated way to extract that, so they don't have to make 63 extractions?
My biggest problem is that every time they make mistakes. It's a lot of things to fill..
Can I create a variant and send it to them? Is it possible to export my variant so they can import it without the need to fill 63x different data?
Thank you.
When this is a task which takes considerable effort by multiple people each year, then it is something which might be worth automatizing.
First you need to find out where that transaction gets its data from. If you spend some time analyzing and debugging the program behind the transaction, you will surely find which SELECT's on which database table(s) provide that data. If you are lucky, there might even be a function module for it.
Then you just need to write an own ABAP program which performs the same selections.
Now about the interesting part: How to get that data to you. There are several approaches here. The best one depends on your requirements and your technical infrastructure. Some possibilities are:
Let users run the program in foreground, use the method cl_gui_frontend_services=>gui_download to save the data to a file on the user's PC and ask them to send it to you via email
Run the program in background and save the file on the application server. Then ask your sysadmins how to get that file from their application server to you. The simplest way would be to just map a network fileserver so they all write to the same place, but there might be some organizational hurdles in the way which prevent that. (Our security people would call me crazy if I proposed to allow access to SMB shares from outside of our network, but your mileage may vary)
Have the program send the data to you directly via email. You can send emails from an SAP system using the function module SO_NEW_DOCUMENT_ATT_SEND_API1. This of course requires that the system was configured to be able to send emails (which you can do with transaction code SCOT). Again, security considerations apply. When it's PII or other confidential data, then you should not send it in an unencrypted email.
Use an RFC call to send the data to your own SAP system which aggregates the data
Use a webservice call to send the data to your own non-SAP system which aggregates the data
You can create a recording in transaction SM35.
There you fill a tcode (SUIM), start recording, make some input in transaction SUIM and then press 'Execute'. Then you can go back to recording (F3 multiple times) and the system will generate some table with commands (structure is BDCDATA). You can delete unnecessary part (i.e. BACK button click) and save it to use as a 'macro'. Then you can replay this recording and it will do exactly what you did.
Also it's possible to export/import the recording to text file, so you can explore it's structure, write some VBA script to create such recording from your parameters and sent it to users. But keep in mind that blanks are meaningful.
It's a standard tools so there's no any coding in the system.
You can save the selection as a variant.
Fill in the selection criteria and press Save.
It can be reused.
You can also transport Variants if the they have a special name

How to copy ALV layouts between clients in same system?

I have ALV layouts saved in a system where data was present but it is not possible to transport those variants from the testing system (system where test data is present). So I have to create same layout variants in development system which is not possible due to lack of test data. Please provide a way to achieve this.
As far as I know there's no standard way to do this. If there's not many variants I suggest you to copy brainless. (I think you can reproduce every layout options without any data) For many variants to copy you can write a program to upload to the DEV system for time-saving.
Please be careful with this because it modifies standard tables! The
system version, ALV structure should be identical and previous records
of variants should not be present, otherwise the result is unexpected!
SAP stores ALV variants in tables LTDX and LTDXT. LTDX contains the variant properties in RAW format. You can download the raw data with SE16 to a tab delimited file from the test system and upload with a developed program to the developer system.
Don't use this program to upload to productive or other systems, go
with transporting, use program RKKBALVI. Always try the results after
uploading to developer, always!
The LTDX-RELID is always 'LT' and the LTDX-REPORT is the program's name you are interested in. Don't forget to edit the file to suit your needs (for example remove the headers and mandant if needed). When you check the downloaded file you can see the raw hex dump of the CLUSTD field.
The concept comes from the idea that you can move HEX content easily from a string type to a binary type field. See this example taken from a little example program in debugger. ('41424150' in HEX = 'ABAP' in ASCII)
So you have to develop a program to upload the contents of the downloaded files to LTDX and LTDXT with cl_gui_frontend_services=>gui_upload but defining the import structures's CLUSTD field as string first. When you imported the data you can move the contents to the real LTDX structure and update the table.
The question of layout transportation is reviewed rather clearly in note 551178 aka FAQ: ALV layout.
Yes, you can transport ALV layouts to another system unless they are user-specific. This is done in ALV layout administration via Customizing request:
Main Menu -> Settings -> Layout -> Administration
User-specific layouts are not transportable, only all-users layouts have this feature.
You can also use program RKKBALVI to copy layouts between clients. For example, we have to develop & configure in client 100 and ALL transports come from 100, but test in client 600.
So, develop the report, test it in 600 and create layout in 600. Then, in 100, run RKKBALVI, enter the program name and execute. From there (list will likely be empty), use menu option Environment > Import layout. It will ask for the Source Client, enter your test client. Select the layouts you want to copy then use the Import icon (or F8).
This will copy the layouts to your client, in our case 100. Then I can use this same program to add them to a transport. So, I can now release my transports from 100 to transport both the report and the layout.

Exchanging work before accurev promote

My colleague and I are participating in a huge project located in Accurev. We've already created own workspaces backed with some stream (let's call it zzz-stream) which is used by many other participants, not only by us.
The point is that we want to exchange our work between our workspaces, make some changes, exchange again, etc. BEFORE making the changes accessible for others, i.e. in other words we don't want to propagate our changes until it is stable and tested, but we want be able to work on it together.
My idea was to create new stream (yyy-stream) backed with zzz-stream, and then change our workspaces to be backed with yyy-stream. But unfortunately I have no rights to create streams.
My second idea was to use a workspace as backed stream, but it doesn't work because Accurev can't use ws as backed stream.
Is there any solution for our problem?
UPD: I accepted Brad's answer as most detailed. However Accurev is too heavy and sluggish to be used effectively. So actually I prefer to use Git for internal needs over the accurev workspace. (see Accurev externally, git internally)
Your idea of creating the yyy-stream is the EXACT right way to do it. The other options are decent workarounds for one-off situations, but creating the extra stream is simple and is fully leveraging AccuRev's capabilities.
That being said, I understand that your admins have stream creation locked down. They of course want control, but should be allowing for maximizing developer productivity and not forcing workarounds like this. My guess is they have stream creation locked down to a particular group being enforced by the server-admin trigger. One common thing I have seen other large sites do is:
- allow streams to be freely created off of a list of acceptable streams (easy to do in the trigger)
- enforce naming rules on the stream creation. This is important to admins in large sites to keep things organized. Again, this is very easy to enforce via the server-admin trigger.
Bottom line, if this is a common situation, work with the admins to allow this capability as per the above. If they have any questions, they are more than welcome to contact AccuRev and we will help them out.
Your idea on using another stream for you and your peer is a good one and is commonly called a collaboration stream. If your site has stream creation locked down, you would need to work with your AccuRev administrator to make that happen.
Another option is for you and the other developer to pull the keeps from the other workspace into your own stream. This relies on both of you being diligent about doing keeps and then you can look at the history of the other developer's workspace to find the keep operation, right-click that transaction and then select Send to Workspace. The destination workspace must be your own.
A third option (more for a situation where you are in your workspace and know exactly what file you want to grab the other users changes)is to bring up the version browser for the file, right click and select history/browse versions. Look for the other workspace, highlight the version in that workspace, right click and select send to workspace. This will checkout that version into your workspace.
This is similar to the change palette suggestion but quicker if your looking to this on a file basis.
Another idea is to use different version control system (e.g. git or svn) over Accurev workspace to exchange the changes and keep our history separated from zzz-stream. (similar to Accurev externally, git internally) Only changed files should be added to other VCS, not whole project. Some merge problems occur though.

How to tracking process's status in Tibco?

I hope you show me resolve in my case.
When I define many process, how to get status data's tracking of that process. In other word, I want to get process's history. My purpose to show for my client checking.
I have defined a process communicate 3 applications and i deploy it to client.but unfortunately, my client would like to add more an application ( up to 4 apps) in the future. i wonder if how to do that? i perhaps open process again and edit it. Have a way create dynamic process.
Thanks very much.
PVA.
You get a very limited "history" in TIBCO Administator (more or less which process instances completed with success/failure; in case of failure it will also provided the exception and where in the process it failed). However that doesn't show you any tracking of the individual steps/activities that the process passed through. For this, you'd either have to put lots of logging steps into your process (and need to build something that parses this information from log files). Or you could use BusinessWorks ProcessMonitoring, which gives you a full history trail for each process automatically. However it not included with BW and you'll probably need a separate license.
Change the process in TIBCO Designer, build a new ear file, re-deploy the new EAR file in TIBCO Administrator.

How to store configuration data so that to not copy it during database copy?

There are parameters that I would not want to be transferred from production environment to QA system. Staff like network path and url's. The problem is that in ABAP everything is in the database and when the database is copied to the QA system you have to manually change those parameters. And this is prone to errors.
Is there a way to store configuration information in a way that won't get transferred with the database?
Thanks.
In short: no - at least that would be very unusual in a SAP environment.
If your QA system is set up as a system copy of your production environment (which is the usual path), there are quite a few steps to do to make the system work correctly. This includes some configuration, which can be as simple as filepaths such as you mention, but also the addresses and names of "partner systems". For example, one of my customers is a bank, so when copying his production system, he makes triply sure that no activity on the QA side accidentally trickles to the production side. Some other changes are made as well, for example obscuring peoples names and addresses so no mail gets accidentally sent etc.
There are a few ways to make applying these changes as easy as possible (look for some SAP documentation or books on SAP Transport and Change management, I had one by Sue McFarland Metzger or so that was quite good). From what I've seen, there is usually a set of transports that change the configuration and customizing etc. on the QA system to the
appropriate values.
Hope that helps.
You cannot prevent the configuration stored in the database from being copied to the cloned instance. However, you can design the configuration storage in a way that will prevent the copied entries from being used. You should check with your basis administrators if they can guarantee that the cloned system will get a new system ID (SID). If this is the case, then you can simply use the SID as key field in your configuration table. After the system copy, the SID will be changed and the cloned system will no longer access the original entries.
your question is not clear, are you talking about standard or custom config ?
Greetings, assuming you are storing these paths in a Z table, then some shops put the sy-sysid ( system id ) as one of the columns. Maintain all systems in your dev and transport to production. This becomes painful after a while, so I would only suggest this for information that does not change a lot ( file paths might be good ).
T.